AGENDA - Port Commission Regular Meeting, July 26, 2011 Page 2
5. UNANIMOUS CONSENT CALENDAR Continued
b. Authorization for the Chief Executive Officer to prepare design and construction bid documents, using Port Engineers to design the
replacement of approximately 167,000 square feet of roof systems located at the Fire Station and on the north end of the Main
Terminal at Seattle-Tacoma International Airport. This authorization is for $200,000 of a total estimated project cost of $4,770,000 (CIP
#C800459). (memo and map enclosed)
c. Authorization for the Chief Executive Officer to advertise and execute a major construction contract for the United States Postal Service
(USPS) Demolition Project at Seattle-Tacoma International Airport and authorize Port Construction Services to self-perform work in
support of the USPS Demolition project. The amount of this request is $5,605,000, and the total cost of the project is $43,900,000.
(WP #104110/CIP #C800254). (memo and attachment enclosed)
d. Authorization for the Chief Executive Officer to issue a contract amendment to the Port of Seattle’s existing Elevator and Escalator
Maintenance Contract for the balance of the 2011 calendar year. This amendment provides additional repair and maintenance
workers to be on duty to respond to escalator outages during the construction project and will increase the monthly cost of the existing
contract by $130,115 for the five remaining months of 2011 beginning in August. The amount of this request is $650,575, which makes
the total estimated cost of the work $3,965,891. Commission previously authorized $3,315,316 of the total in the 2011 budget. (memo
enclosed)
e. Authorization for the Chief Executive Officer to proceed with executing service agreements, preparations of construction documents,
project management and permitting tasks for the design phase of Terminal 91, C-175 Building Roof Replacement Project. The amount
of this request is $190,000, bringing the current authorization for the project to $240,000 for a total estimated project cost of $2,445,000
(CIP #C800430). (memo enclosed)
6. DIVISION, CORPORATE AND COMMISSION ACTION ITEMS
a. Authorization for the Chief Executive Officer to execute a professional services indefinite delivery/indefinite quantity contract to perform
continuous process improvement services with a total value of $300,000 and contract duration of two base years plus two individual
option years for a total of four (4) years. No budget authorization request is associated with this authorization. (memo enclosed)
b. Authorization for the Chief Executive Officer to execute (1) a project specific contract to assist Port staff on the runway 16C/34C
replacement not to exceed $1,000,000, until the project is completed, and (2) an indefinite delivery/indefinite quantity contract for
airfield technical support assistance not to exceed $1,750,000 over 4 years for various upcoming airfield operational and safety
evaluations, evaluation of tenant and Federal Aviation Administration projects that may affect airfield operations, and capital
improvement projects at Seattle-Tacoma International Airport. The total value of contracts is $2,750,000, but no funds are requested
at this time. (memo, attachment, and PowerPoint enclosed)
c. Authorization for the Chief Executive Officer to modify the Scope of Work for the Runway 16C/34C Surface Panel Replacement project
by extending the project period through the end of 2012, and approval of the use of $200,000 of the previously authorized funds to
prepare design documents for a surface panel replacement construction contract to be advertised and constructed in 2012. The total
cost of this project is $4,169,262 (CIP #C800112). (memo enclosed)
d. Authorization for the Chief Executive Officer to complete the design and perform any advance work in support of the 2012 Pavement
and Joint Sealant Project for non-runway concrete pavement panels and joint seal replacement, spall repair and associated or
temporary facilities, such as striping, lighting, etc., on the Aircraft Operations Area in anticipation of a 2012 construction contract.
Budget requested for this work is $465,000 out of an estimated total program cost of $30,800,000 for the multi-year program (CIP
#C102573). (memo and attachment enclosed)
e. Authorization for the Chief Executive Officer to issue a change order for the Consolidated Rental Car Facility project to extend the
completion date by an amount not to exceed 80 calendar days. Although the Port has received a claim for additional costs related to
schedule delay, this extension would specifically not, at this time, be compensable to the general contractor/construction manager or
any subcontractors (MC-0315405). (memo enclosed)
f. Authorization for the Chief Executive Officer to execute a project specific contract to support Concessions Planning and Leasing
Services at Seattle-Tacoma International Airport. The services to be provided under this procurement are estimated at a maximum of
$3.0 million for three years with a one two-year extension option. No budget is associated with this authorization. Budget will be
included within annual budget requests that are reviewed and approved by the Commission. (memo and attachment enclosed)