
COMMISSION AGENDA – Action Item No. 8m Page 2 of 4
Meeting Date: November 17, 2026
Template revised June 27, 2019 (Diversity in Contracting).
Maritime Blue has requested an additional six months to finalize its funding to perform their tenant
improvement work. Currently, Maritime Blue has verbal commitments of 100% for its capital funding with
these becoming signatories in November and anticipate Tenant Improvements to commence January
2027. This six-month extension would further adjust the Rent Commencement Date from December 17,
2026, to June 16, 2027 and the Early Termination Outside Completion Date (for TI) from March 18, 2027,
to September 18, 2027. The primary term of the lease would be extended by six months from June 15,
2036, to December 15, 2036. By extending the term by six months there is no loss of net revenue for the
Port during the primary term of the lease.
Additionally, the Port was unable to install all of the required solar panels for the living building challenge
during the MInC project due to a delay in the delivery of approximately half the solar panels with their
installation significantly impacting the timing of the substantial completion of the MInC project and timely
delivery of the Premises to Maritime Blue resulting in significant penalties. The intent was to install them
as a separate project. However, performing the installation of the solar panels after the completion of the
MInC project would require a new permit and contract resulting in significant delays and not be completed
in coordination with the tenant improvements causing delays in the LBC 12-month monitoring
requirements. To meet and expedite the LBC monitoring requirements, Maritime Blue has agreed to
complete the installation of the remaining solar panels as a part of their tenant improvements, relieving
the Port of its obligation to install the remaining solar panels as a part of the “Lessor’s Work” under the
lease terms and conditions subject to reimbursement by the Port. This will allow for timely coordination
of the living building challenge monitoring to achieve living building certification. Therefore, the First
Amendment would include an additional tenant improvement allowance to reimburse Maritime Blue in
an amount not to exceed $300,000 for the installation of the additional solar panels.
ALTERNATIVES AND IMPLICATIONS CONSIDERED
The timely installation of the solar panels is required to commence with the living building
challenge 12-month monitoring for the living building challenge certification.
Alternative 1 – Port procures and installs the solar panels
Cost Implications: $285,000
Pros:
(1) Port would have control over the installation.
Cons:
(1) Would require a long-lead time for a new permit and contract for installation.
(2) Would more than likely not align with completion of tenant improvements with strong
potential to delay living building challenge monitoring required for LBC certification.
(3) Would require extended overheads including permit and associated costs with Port
contracted installation.
This is not the recommended alternative.