Current Budget: $78,240,000
This Request: $4,700,000
Revised Budget: $82,940,000
The request supports the Port’s
obligations for construction
completion and closeout
The project is funded by the
Airport Development Fund
Schedule Milestones:
• Construction Auth: Q3, 2021
• South Loop In Use: Q2, 2027
• North Loop in Use: Q1, 2028
• Substantial Completion: Q3, 2028
Schedule extended by 31 months
due to a construction contractor
defaulting and additional
manufacturing delays.
Project Budget and Schedule
4