Item No. Date of Meeting 2027 Airfield Projects Construction Authorization (CIP # C801379) Seattle-Tacoma International Airport 8f_supp October 13, 2026 2027 Airfield Projects • Request Commission authorization for the Executive Director to take all steps necessary to complete two construction contracts for 2027 Airfield Projects and limited utility installation scope on behalf of the S Concourse Evolution (SCE) Program located at Cargo 7 hardstand area. • The total amount of this authorization request is $40,000,000 CIP Name/# Amount of this Request Total Estimated Project Cost 2026-2030 Airfield Pavement and Supporting Infrastructure Replacement Program C801379 $40,000,000 $400,000,000 2 Justification • 2027 Airfield Projects are part of 2026-2030 Airfield Program: - Airfield infrastructure renewal and replacement & Projects needed to provide safe and efficient conditions for aircraft operations at SEA and meet FAA and other regulatory requirements. • Cargo 7 utility scope as part of the SCE Program was designed and phased to be delivered concurrently with the 2027 Airfield scopes - Overlapping design functionality, interdependent operational impacts, and shared 2027 schedule milestones; - For purposes of Airfield safety, efficiency, and minimization of operational impacts. 3 2027 Airfield Contract #1 - Federally Funded • 2026-2030 Airfield Program (CIP #C801379) - Replacement of aging and failing utilities, non-standard flush fire hydrant access hatches, electrical circuits, lighting fixtures and signs at RW 16R/34L, connecting taxiways, infield areas and vehicle service road; - Removal of turf edge dams, mitigation of ponding spots and installation of anti-perching devices at RW 16R/34L, connecting taxiways and infield areas. Entitlement Funds Anticipated in 2027: ~$10,960,000 4 2027 Airfield Contract #2 • 2026-2030 Airfield Program (C801379) - Replacement of distressed pavement at TW B, Taxilane W, Apron and Cargo areas. • S Concourse Evolution Program (C801203) - Installation of power and communication utility duct bank at Cargo 7 area. 5 2027 Airfield Projects Map 6 2026-2030 Airfield Program Overview 2027 2029 2026 2028 2030 7 2027 Airfield Projects Schedule Construction Contract # Contract #1 Contract #2 Construction start 2027 Quarter 2 2027 Quarter 2 In-use date 2027 Quarter 4 2027 Quarter 4 8 2027 Airfield Projects Budget CIP Name/# Amount of this Request 2026-2030 Airfield $40,000,000 Pavement and Supporting Infrastructure Replacement Program C801379 Total Authorization of this $40,000,000 Request Amount Total Authorized to Estimated Date, incl. Project Cost this Request $175,698,000 $400,000,000 9 QUESTIONS? 10