2027 Airfield Contract #1 does not replace or add additional concrete. 2027 Airfield Contract #2
has limited pavement scope for individual concrete panels. For awareness, SEA's concrete meets
FAA design standards and exceeds industry standards for solar reflectivity minimizing heat island
effect. We also conduct routine maintenance including sweeping and runway rubber removal
that maintains solar reflectivity.
Scope of Work
The 2027 project scope includes replacement of distressed pavement at TW B, Taxilane W, Apron
and Cargo areas; replacement of aging and failing airfield utilities located within the Runway
Safety Area (RSA) for RW16R/34L; replacement of failing non-standard flush fire hydrant access
hatches; renewal and replacement of electrical circuits with low megger readings and installation
of LED lighting fixtures and signs for RW16R/34L and connecting taxiways; removal of turf edge
dams along RW16R/34L, connecting taxiways and access roads; mitigation of water ponding
areas and installation of anti-perching devices within the RW16R/34L RSA.
The 2027 Contract #2 will also construct utility installation scope at Cargo 7 as a facilitating
project on behalf of the SCE program.
Schedule
Activity
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 – Proceed only with federally funded 2027 Contract #1 Airfield work including the
replacement of aging and failing airfield utilities, non-standard flush fire hydrant access hatches,
electrical circuits, lighting fixtures and signs; removal of turf edge dams; mitigation of ponding
spots and installation of anti-perching devices at RW 16R/34L, connecting taxiways, infield areas
and vehicle service road. Do not proceed with the scope in 2027 Contract #2 including
replacement of distressed pavement at TW B, Taxilane W, Apron and Cargo areas, and installation
of power and communication at Cargo 7 area.
Cost Implications: $33M in Cost for 2027 Contract #1.
Pros:
(1) Reduced capital spending in 2027.