COMMISSION AGENDA – Action Item No. 8e Page 2 of 5
Meeting Date: October 13, 2026
Template revised June 27, 2019 (Diversity in Contracting).
to reduce the overall required outage time, streamline electrical cable procurement, and
capitalize on operational and construction efficiencies using a single contractor.
The current procurement lead-time for the required electrical cable is 65 weeks. This funding
authorization will allow for early incorporation of the project into the T91 Uplands Development
Phase 1 project, and rapid procurement of the cable to ensure minimization of impact due to
material lead-time.
JUSTIFICATION
The Port of Seattle T91 Energy and IT Plan, published on September 18
th
, 2026, identified Feeder
205 Replacement as a priority project required to preserve the reliability of power distribution to
some critical elements of the terminal, including Building W-40 (which is occupied by
Independent Packers Corp, a cold storage operation), Lift Station 7, Cruise Parking, and Marine
Maintenance North Operations (MMNO). This project is one of several asset preservation
projects included in the capital plan that will ensure reliable power distribution throughout
Terminal 91.
Feeder 205 was installed between 1997 and 1999. It was tested during an electrical
condition assessment at T91 that was delivered to Waterfront Project Management in January
2026. The resulting measurements showed that insulation resistance readings for the feeder
electrical cables are lower than the industry standard minimum and are at end of service life and
in critical need of repair. Operating Feeder 205 in this condition increases the risk of power
interruptions. If Feeder 205 fails, operational impacts affecting T91 operations, tenant operations
at Building W-40, and the Cruise parking lot would result in costly temporary power
requirements.
Diversity in Contracting
The design-builder for the T91 Uplands Development Phase 1 PDB contract has committed to a
25% WMBE aspirational goal with an additional 5% for veteran owned businesses.
DETAILS
Feeder 205 consists of three (3) electrical cables within a concrete encased duct bank. The project
scope will include removal and replacement of the existing electrical cables for Feeder 205
between Main Substation 2 (electrical source) and Switch SS 7. The electrical cables of Feeder
205 between Maintenance Hole 16 and Substation 5 will also be demolished but not be replaced
in accordance with the recommendations of the Port of Seattle T91 Energy and IT Plan. This work
will require a scheduled temporary power outage to execute. Provisions for temporary power
will be supplied to affected locations during construction.
Because the Terminal 91 Uplands project already planned to replace Feeder 207, the Feeder 205
project can utilize the same contract. This will allow more streamlined procurement.
Coordinating the Feeder 205 work with the Feeder 207 work will also allow for fewer service
alignment disruptions had the two projects been done separately.