Monthly Payment Application Review Service (MPARs) Port of Seattle - Baggage Optimization Project Phase 3 Powered by: Fort Hill's Advanced Digital Analytics Engine delivering 100% Project Cost Analysis. Firm Information Legal Name: Fort Hill Associates, LLC Type of Business: Construction Audit Consultancy State of Formation: South Carolina Website: www.forthillassociates.com Business Organization: Limited Liability Corporation (Partnership) Total Employees: Sixteen (16) with Twelve (12) Construction Auditors Year of Formation: 2006 (20 years in Business) Number of Years of Relevant Experience: 20 years of Relevant Experience Principal Office Location: Greenville, South Carolina Location of Office Performing Services: Greenville, South Carolina Organizational Structure: 1. Engagement Manager: A principal-level resource responsible for overseeing the entire project. 2. Subject Matter Expert (SME): Another principal-level resource, dedicated full-time to the project, ensuring in-depth expertise is applied to every aspect of the work. 3. Audit Manager: Manages the audit process and ensures adherence to best practices and timelines. 4. Senior Managers: Oversee audit pods, which include managers, construction program consultants, and senior consultants who report directly to them. Specializing In: Fort Hill Associates, LLC is a full-service construction audit consultancy, specializing in pre-construction contract reviews and construction contract audits. Fort Hill assists owners of construction projects by ensuring contract compliance through the validation of up to 100% of the transaction costs passed from their Contractors/Construction Managers on their construction projects. Fort Hill's pre-construction contract reviews identify and mitigate issues before they arise. The audits and reviews not only potentially return and save money on an Owner's current project but also create a knowledge base within the Owner's organization of the issues that can arise on future projects. Fort Hill Associates' Office that will support POS Projects: Port of Seattle Primary Contact: Company Principals / Years of Experience: 37 Villa Road, Suite 106 Greenville, South Carolina 29615 Doug Plyler dplyler@forthillassociates.com 37 Villa Road, Suite 106 Greenville, South Carolina 29615 864.640.2518 1. Curt Plyler, Principal 2. Martin Howell, Principal 3. Doug Plyler, Principal 21 years 19 years 19 years 2 Fort Hill Scope to Port of Seattle: Monthly Payment Application Reviews (MPARs) Fort Hill's Monthly Payment Application Reviews allow clients to review payment application reviews in real time. As a result of this initiative, the following opportunities can be realized. 1 Obtain reliable realtime data for enhanced decision-making 2 Leverage information to identify forwardlooking trends 3 Minimize future audit findings by providing real-time observations for management action to enhance payment practices 4 Develop and execute repeatable audit testing based on contract and project documentation 5 100% validation (i.e. no sampling) of all projectrelated costs MPAR Payment Application Process Lifecycle 3 Process FlowFlow MPAR Process Day 1: Payment Application Delivered to Fort Hill by the Port Day 8: Fort Hill Comments Back to Port of Seattle (7 Day Turnaround) Post Audit: Fort Hill Comments Reviewed with Clarification Sent Back to Fort Hill 4 Examples Findings Examples of of Findings  Discrepancy in Billed Amounts Between Calculation Error in G703  Discrepancy in Billed Amounts Between Payment Applications  Missing Supporting Documentation  Discrepancy in Employee Billing Hours  Asset Tracking & Verification  Insufficient Supporting Documentation  Inaccurate Equipment Rates Missing Rate Support for Labor Billings Potential Non-Reimbursable Charges 5 Examples of Findings Example of Report  Payment Application #5  Received from the Port on January 26, 2026  Fort Hill Review Sent to the Port on February 2, 2026  Report on Following Pages 6 Monthly Payment Application Review Service (MPARs) Port of Seattle - Baggage Optimization Project Phase 3 January 06, 2025 Payment Application #5 Payment Application Amount $ 2.978 Million Powered by: Fort Hill's Advanced Digital Analytics Engine delivering 100% Project Cost Analysis. This Month's Observations  Missing Supporting Documentation: Construction Manager billed $ 134,607 under Bid Subs. However, supporting documentation(invoices, receipts, Payment Application) is not available for the review. Audit requests the Construction Manager to provide the necessary supporting documentation (invoices, receipts, Payment Application) and additional information for verification. Item No. Subsytem Description of Work This Period $ 38,645.00 10 1 Fire Suppression $ 31,731.00 12 2.02 Beam Strengthening $ 11,106.00 13 2.03 Structural Steel & Misc Metals $ 35,625.00 17 2.08 Plumbing and Piping $ 17,500.00 18 2.09 HVAC $ 134,607.00 Total  Missing Supporting Documentation: Construction Manager billed $ 69,932.57 in "WA #023 - Scaffold Protection" under NSS (Negotiated Support Services); however, the supporting documentation substantiates only $ 63,932.57, resulting in a variance of $ 6,000 . Audit requests the Construction Manager to reconcile this variance. G703- NSS Schedule of Values "WA #023 - Scaffold Protection" $ 69,932.57 Summary Description Pg No-47 "WA #023 - Scaffold Protection" $ 63,932.57 Description $ 6,000.00  Discrepancy in Employee Billing Hours - Integrated Design Engineers: Construction Manager billed hours totaling 131 as reflected in the Integrated Design Engineers invoice, however, as per the timesheets the calculated total is 123 hours, resulting in a deviation of $1,114.50. Description Principal Structural Engineer: Ignasius Seilie $ Lead Structural Design Engineer: Iris Xu $ Design Engineer: Derek Imperial $ Hours Billed 285.00 9 150.00 67 121.50 55 Total Billed Rate Amount Billed $ $ $ $ 2,565.00 10,050.00 6,682.50 19,297.50 Hours as per Timesheets 9 62 52 Hours Deviation 0 5 3 Amount Deviation $ $ $ $ 750.00 364.50 1,114.50 8 This Month's Observations  Discrepancy in Billed Amounts Between Calculation Error in G703: Audit observed calculation errors in the below submitted G703 forms by Construction Manager. 1.) MASC Schedule of Values 2.) NSS Schedule of Values Construction Manager is requested to correct the errors. MASC Schedule of Values Work Completed Total Completed & Stored to Date Description of Material Scheduled Value Presently Stored Work from Previous Application This Period Actual Calculated Deviation $ 8,254,670.47 $ (36.00) $ 6,483,918.54 $ 1,770,751.93 $ 8,254,634.47 ECCM - VECA $ 96,393,670.36 $ 12,731,330.13 $ (36.00) $ 9,606,353.00 $ 10,825,971.20 $ 1,905,358.93 $ $ 12,731,294.13 TSC $ 26,109,844.01 $ (36.00) $ 23,131,754.46 $ 2,978,089.55 $ $ 26,109,808.01 MACC Total $ 432,799,192.36 Description of Work Temporary Utilities and Structures $ GCCM Negotiated Support Services Total $ NSS Schedule of Values Authorized Value Actual 51,743.00 $ 8,836,461.38 Authorized Value Calculated $ Deviation 73,215.00 $ 21,472.00 8,857,933.38 $ 21,472.00  Discrepancy in Billed Amounts Between Payment Applications: The amount billed for the previous period in Payment Application #5 is $ 23,131,754.46 and the Total Completed & Stored in Payment Application #4 was $ 23,654,274.92, resulting in a variance of $ 522,520.46. This discrepancy in the reported values between the two payment applications requires additional supporting information. Audit requests the Construction Manager to submit the revised Payment Application#4 for reconciliation and record purpose. PA#5 Work Previously PA#4 Total Completed & Item No. Subsytem Description of Work Deviation Completed Stored 1 2 3 6 7 8 19 20 21 Hensel Phelps SC/CM - Daifuku ECCM - VECA HPCC Fee (6.85%) General Conditions GCCM NSS Change Orders Fee NSS Fee TSC MACC Total $ 4,949,161.63 $ 5,574,160.40 $ (624,998.77) $ $ $ $ $ $ $ $ $ $ 4,494,798.94 368,373.15 488.73 4,158,971.66 6,483,918.54 7,356,621.63 7,331,388.07 25,233.57 10,825,971.20 23,131,754.46 $ 5,120,838.34 $ 367,821.25 $ $ 4,148,134.19 $ 6,567,400.12 $ 7,181,499.21 $ 7,160,045.57 $ 21,453.64 $ 10,898,615.31 $ 23,654,274.92 $ $ $ $ $ $ $ $ $ $ (626,039.40) 551.90 488.73 10,837.47 (83,481.58) 175,122.42 171,342.50 3,779.93 (72,644.11) (522,520.46) 9 This Month's Observations  Missing Rate Support for Labor Billing: Construction Manager billed $ 11,141.44 for labor under Negotiated Support Services; however, the agreed-upon hourly rates were not available for verification. Audit requests the Construction Manager to provide the applicable agreed-upon hourly rates to facilitate review and reconciliation of the billed amount. Description Name Pineiro Stephen Vigil, Loren WA#016-Construction Fibbs, Jonathan Progress Cleaning Pineiro, Stephen McClain, Wilber Davis, James WA #023 - Scaffold Pineiro, Stephen Protection Pineiro, Stephen Davis, James WA #038 - Break Area Pineiro, Stephen Relocation Designation Washington Laborers - Group 3 General Laborer Washington Carpenters - Foreman Washington Carpenters - Appr 7th Period 90% Washington Laborers - Group 3 General Laborer Washington Laborers - Foreman Group 3 Washington Laborers - Foreman Group 3 Washington Laborers - Group 3 General Laborer Washington Laborers - Group 3 General Laborer Washington Laborers - Foreman Group 3 Rate Type ST ST ST ST ST ST ST ST ST $ $ $ $ $ $ $ $ $ Billed Rate 75.12 100.56 86.17 75.12 80.07 80.07 75.12 75.12 80.07 Washington Laborers - Foreman Group 3 ST $ 75.12 Hours 20 4 4 30 3 25.00 30.00 10.00 8.00 Billed Amount $ 1,502.40 $ 402.24 $ 344.68 $ 2,253.60 $ 240.21 $ 2,001.75 $ 2,253.60 $ 751.20 $ 640.56 10 $ 751.20 Total $ 11,141.44 Page No 35 36 37 38 39 48 49 50 51 72  Potential Double Billing of Tax: Construction Manager applied Washington State Tax at 10.20%, totaling $ 303,761.46 in this Payment Application #5. However, a separate tax amount of $ 16,604.45 is also included within the Negotiated Support Services (NSS) and Cost of Work (COW). Audit requests the Construction Manager to provide clarification regarding the application of the 10.2% Washington State Tax on the $ 16,604.45 (Refer Annexure-A) sales tax amount.  Potential Non-reimbursable Charges: Construction Manager billed cumulative total of $ 4,204.94 for IT charges. However, as per the Document 00 SO 01 Summary Matrix of Cost Allocation, IT charges are part of Specified General conditions. Audit requests the Construction Manager for clarification regarding the reimbursable nature of the items billed. Cost Category GCCM NSS Page # Pg 17 Vendor CDW Direct Issue Amount $ 714.88 GCCM NSS Pg 17 CDW Direct $ 2,521.03 GCCM NSS Pg 17 CDW Direct Total $ $ 969.03 4,204.94 Description LOGITECH MEETUP LOGITECH RALLY PLUS SOLUTION LOGITECH TAP CONTROLLER W/CAT5E KIT 10 This Month's Observations  Missing Rate Support for Labor Billing: Construction Manager billed $ 11,141.44 for labor under Negotiated Support Services; however, the agreed-upon hourly rates were not available for verification. Audit requests the Construction Manager to provide the applicable agreed-upon hourly rates to facilitate review and reconciliation of the billed amount. Description Name Pineiro Stephen Vigil, Loren WA#016-Construction Fibbs, Jonathan Progress Cleaning Pineiro, Stephen McClain, Wilber Davis, James WA #023 - Scaffold Pineiro, Stephen Protection Pineiro, Stephen Davis, James WA #038 - Break Area Pineiro, Stephen Relocation Designation Washington Laborers - Group 3 General Laborer Washington Carpenters - Foreman Washington Carpenters - Appr 7th Period 90% Washington Laborers - Group 3 General Laborer Washington Laborers - Foreman Group 3 Washington Laborers - Foreman Group 3 Washington Laborers - Group 3 General Laborer Washington Laborers - Group 3 General Laborer Washington Laborers - Foreman Group 3 Rate Type ST ST ST ST ST ST ST ST ST $ $ $ $ $ $ $ $ $ Billed Rate 75.12 100.56 86.17 75.12 80.07 80.07 75.12 75.12 80.07 Washington Laborers - Foreman Group 3 ST $ 75.12 Hours 20 4 4 30 3 25.00 30.00 10.00 8.00 Billed Amount $ 1,502.40 $ 402.24 $ 344.68 $ 2,253.60 $ 240.21 $ 2,001.75 $ 2,253.60 $ 751.20 $ 640.56 10 $ 751.20 Total $ 11,141.44 Page No 35 36 37 38 39 48 49 50 51 72  Potential Double Billing of Tax: Construction Manager applied Washington State Tax at 10.20%, totaling $ 303,761.46 in this Payment Application #5. However, a separate tax amount of $ 16,604.45 is also included within the Negotiated Support Services (NSS) and Cost of Work (COW). Audit requests the Construction Manager to provide clarification regarding the application of the 10.2% Washington State Tax on the $ 16,604.45 (Refer Annexure-A) sales tax amount.  Potential Non-reimbursable Charges: Construction Manager billed cumulative total of $ 4,204.94 for IT charges. However, as per the Document 00 SO 01 Summary Matrix of Cost Allocation, IT charges are part of Specified General conditions. Audit requests the Construction Manager for clarification regarding the reimbursable nature of the items billed. Cost Category GCCM NSS Page # Pg 17 Vendor CDW Direct Issue Amount $ 714.88 GCCM NSS Pg 17 CDW Direct $ 2,521.03 GCCM NSS Pg 17 CDW Direct Total $ $ 969.03 4,204.94 Description LOGITECH MEETUP LOGITECH RALLY PLUS SOLUTION LOGITECH TAP CONTROLLER W/CAT5E KIT 11 This Month's Observations  Inconsistency in Hourly Billing Rates: VECA (Electrical Contractor) billed amount totaling $ 16,638.36 for field employees. However, the agreed-upon hourly rate for the employee (Labor Rates For Rate Period 08/04/2025 Through 12/31/2025) do not align with the billed rates, resulting in a variance of $ 8,074.39. Audit requests the Electrical Contractor to provide additional supporting information for the reconciliation. End Date Work Date Phase SOV Item 11/23/25 12/04/25 000-04080 NEW CONVEYORS LABOR 12/07/25 12/01/25 000-04080 NEW CONVEYORS LABOR 12/04/25 11/16/25 Phase Name Employee Name Page # Agreed Rate Rate Deviation Amount Deviation 9,184.50 Pg 89 $ 31.51 $ 29.72 $ 4,458.00 106.26 $ 106.26 Pg 90 $ 56.27 $ 49.99 $ 61.23 $ 7,347.60 Pg 132 $ 31.51 $ 29.72 $ 3,566.40 Total $ 8,074.39 Title Shift Hours Rate Amount Billed WAREHOUSE / MASON T STOCKMAN WITKOSKI STOCKMAN LVL 1 1 150 $ 61.23 $ WAREHOUSE / DREW K STOCKMAN SHERWOOD STOCKMAN LVL 1 1 1.00 $ Construction GARBAGE DREW K Dumpsters, Waste, DISPOSAL/RE 000-00822 SHERWOOD Recycling and Debris MOVAL Removal STOCKMAN LVL 1 1 120.00 $ Remarks Conisdered Rate as per Stockman Level 1 (0-3000 hrs) Conisdered Rate as 49.99 per Stockman Level 1 (0-3000 hrs) - DT Considered Rate as per Stockman Level 1 (0-3000 hrs)  Missing Hourly Rates for Field Labor: VECA (Electrical Contractor) billed a cumulative total of $ 19,948 for the field employee Gordon E Allen JR, however, the agreed upon hourly rate for the employee is not available for review. Audit requests the Electrical Contractor to submit the agreed-upon hourly rates for verification and reconciliation. End Date Work Date Phase SOV Item Phase Name Employee Name 11/16/25 BIM Management, BIM GORDON E 12/02/25 000-00800 Staffing, Equipment SUPPORT/CO ALLEN JR License, Program Costs ORDINATION Title PT Hours ELEC FOREMAN R 120.00 $ Rate Amount Billed W/ SMALL TOOLS Page # 166.24 $ 19,948.80 $ 20,946.30 Pg 133  Clarification Required on Applicable Rate Sheet - Warehouse Stockman: VECA (Electrical Contractor) billed $ 7,670.04 for the Warehouse Stockman. However, two different rate sheets have been submitted-one during the previous audit and another within Payment Application #5. Audit requests the Subcontractor to confirm which rate sheet should be used for review and reconciliation of the billed amount. End Date Work Date Phase 11/23/25 11/21/25 000-04080 SOV Item Phase Name Employee Name NEW CONVEYORS - WAREHOUSE TIMOTHY G LABOR / STOCKMAN DUCLOS Union LOCAL_46 Title STOCKMAN FOREMAN Shift PT Hours Rate AMOUNT Page # 1 R 92.00 $ 83.37 $ 7,670.04 Pg 89 12 This Month's Observations  Inconsistency in Hourly Billing Rates - Juice Company: VECA (Electrical Contractor) billed amount totaling $ 3,166.08 for field employees under Juice Company. However, the agreed-upon hourly rate for the employee (Labor Rates For Rate Period 08/04/2025 Through 12/31/2025) do not align with the billed rates, resulting in a variance of $ 16.15. Audit requests the Electrical Contractor to provide additional supporting information for the reconciliation. WORK DATE PHASE NAME EMPLOYEE NAME DAVE MONTENEGRO DAVE 11/13/2025 LOGISTICS MONTENEGRO DAVE 11/14/2025 LOGISTICS MONTENEGRO DAVE 11/24/2025 LOGISTICS MONTENEGRO 11/10/2025 LOGISTICS 11/26/2025 LOGISTICS JACK OSARA 12/1/2025 LOGISTICS DAVE MONTENEGRO 12/1/2025 LOGISTICS JEFFREY TAYLOR 12/1/2025 LOGISTICS JEFFREY TAYLOR UNION TITLE SHIFT PT HOURS ELEC GENERAL LOCAL 46 FOREMAN ELEC GENERAL LOCAL 46 FOREMAN ELEC GENERAL LOCAL 46 FOREMAN ELEC GENERAL LOCAL 46 FOREMAN ELEC LOCAL 46 JOURNEYMAN ELEC GENERAL LOCAL 46 FOREMAN ELEC LOCAL 46 JOURNEYMAN ELEC LOCAL 46 JOURNEYMAN HOURLY RATE Amount Billed Agreed Rate Rate Deviation Amount Deviation 1 R 4 $ 142.44 $ 569.76 $ 141.73 $ 0.71 $ 2.84 1 R 2 $ 142.44 $ 284.88 $ 141.73 $ 0.71 $ 1.42 1 R 2 $ 142.44 $ 284.88 $ 141.73 $ 0.71 $ 1.42 1 R 5 $ 142.44 $ 712.20 $ 141.73 $ 0.71 $ 3.55 1 R 2 $ 124.10 $ 248.20 $ 123.42 $ 0.68 $ 1.36 1 R 4 $ 142.44 $ 569.76 $ 141.73 $ 0.71 $ 2.84 1 R 3 $ 124.10 $ 372.30 $ 123.42 $ 0.68 $ 2.04 1 R 1 $ 124.10 $ 124.10 $ 123.42 $ 0.68 $ 0.68 $ 16.15 Total $ 3,166.08 Total Remarks Considered rate as per Electrical Wireman - General Foreman Considered rate as per Electrical Wireman - General Foreman Considered rate as per Electrical Wireman - General Foreman Considered rate as per Electrical Wireman - General Foreman Considered rate as per Electrical Wireman - JW Considered rate as per Electrical Wireman - General Foreman Considered rate as per Electrical Wireman - JW Considered rate as per Electrical Wireman - JW  Inconsistency in Equipment Rates: VECA (Electrical Contractor) billed amount totaling $ 723.20 for its owned equipment. However, the agreed-upon hourly rate (Equipment Watch Rate Sheet) do not align with the billed rates, resulting in a variance of $ 296.20. Audit requests the Electrical Contractor to provide additional supporting information for the reconciliation. ID Category Hourly (Billed) 032010-007 03210-116 032010-124 032010-176 032010-092 Conduit/bunk Cart Conduit/bunk Cart Conduit/bunk Cart Conduit/bunk Cart Conduit/Bunk Cart 0.44 0.44 0.44 0.44 0.68 Mode Description Monthly Total (Hours) OPERATING OPERATING OPERATING OPERATING OPERATING 2023 Sumner 783230 2023 Sumner 783230 2023 Sumner 783230 2023 Sumner 783230 Current Tools 516 300 280 300 300 300 Total Monthy Billed Amount $ $ $ $ $ $ 132.00 123.20 132.00 132.00 204.00 723.20 FHWA (Hourly) $ $ $ $ $ 0.25 0.25 0.25 0.25 0.44 Rate Deviation Amount Deviation $ $ $ $ $ $ 57.00 $ 53.20 $ 57.00 $ 57.00 $ 72.00 $ 296.20 0.19 0.19 0.19 0.19 0.24 Total Considered Rate Ref Page # Pg 232 Pg 232 Pg 232 Pg 232 Pg 240 13 This Month's Observations  Inconsistency in Billing - Holmberg Mechanical: Construction Manager billed amount totaling $ 3,180 for change order (HP Office Trailer Hookup - T&M work) under Holmberg Mechanical. Audit identified that subcontractor billed Pipe Fitting Foreman at the hourly rate of $135.51, however, the hourly rate for employee does not match with the agreedupon hourly rate, resulting in a deviation of $ 32. Company Description Billed Rate Holmberg Mechanical Local 32 - Plumbing/Pipe Fitting Foreman $ 135.51 Hours Billed Amount 8 $ 1,084.08 Amount Deviation 32.00 131.51 $ Agreed Rate $  Inconsistency in Billing Under COP 005 - Shinn Mechanical: Construction Manager billed $1,202 under change order (24-3880 - COP 005 - PH1 Temp Scaffold ROW FS Demo) for Shinn Mechanical. The audit noted the following discrepancies: • Labor Charges: Subcontractor billed $602.24 for field employees; however, the employee designations in the Payment Application do not align with those listed in the approved rate sheet (Filename: Submittal 012000-07-0 - Labor rates - SHINN). • Equipment Charges: o Subcontractor billed $ 153.16 for standard pickup trucks at the rate of $38.29/hour. The hourly rate billed does not match the rate provided in the approved equipment rate sheet (File Name: Submittal 012000-08-0 - Equipment Rates - SHINN), resulting in a variance of $ 88.40. o Subcontractor billed $ 5.03 for Pipe Cart, however, approved rate is not available for verification. • Material Charges: A total of $148.61 was billed for materials; however, no supporting documentation (invoices, receipts, etc.) was available for audit review. Audit requests the Construction Manager to provide clarification and supporting documentation for reconciliation & verification. Cost Category Labor Labor Equipment Materials Designation Apprentice Design Total Standard Pickup Truck Pipe Cart Total Billed Rate $ 86.57 $ 127.98 Hours 4 2 $ 38.29 $ 5.03 4 1 Billed Amount $ 346.28 $ 255.96 $ 602.24 $ 153.16 $ 5.03 $ 158.19 $ 148.61 Agreed Rate $ 16.28 Missing Rate Amount Deviation $ 88.04 14 This Month's Observations  Inconsistency in Billing - Hensel Phelps: Construction Manager billed $ 56,696.41 under Engineered and Supplied Modular Bull Rail Members. The audit noted the following discrepancies: • Potential Overbilling in Markups - Construction Manager billed amount totaling $ 56,696.41 inclusive of $ 9,449.40 markup at the rate of 20%, however, the as per the Table: Cost Categories & Markups of Contract Agreement the markup is 5% for self-performed NSS Works, resulting in a variance of $7,087.05. • Potential Lump Sum - Construction Manager billed amount totaling $ 39,335 for Bull Rail Materials, however, the itemized breakdown of the cost was not available for review. Audit requests the Construction Manager to confirm whether this is a lump sum charge or to submit a detailed breakdown to support the billed amount. Vendor Hensel Phelps $ Base Amount Markup Billed 47,247.01 $ 9,449.40 Actual Markup @5% $ 2,362.35 $ Deviation 7,087.05 Page No 60  Inadequate Supporting Documentation: VECA (Electrical Contractor) billed $791.93, inclusive of a 5% charge for small tools. However, the supporting documentation lacks sufficient itemized detail to determine the reimbursable nature of the expense. Audit requests the Electrical Contractor to submit the additional supporting information for the billed expenses. Post Date Invoice Date 11/01/25 10/30/25 000-00818 11/01/25 11/01/25 Phase SOV Item Amount Billed Phase Name Vendor Invoice No Site Security for your work, and for your work areas SITE SECURITY AMAZON 1030202512 $ 50.86 10/17/25 000-00818 Site Security for your work, and for your work areas SITE SECURITY AMAZON 1018202545 $ 176.31 10/13/25 000-00818 Site Security for your work, and for your work areas SITE SECURITY 1013202525 $ 528.93 Total $ 756.10 AMAZON W/ Small Tools Remarks Inadequate insufficient 53.40 documentation: No actual invoice Inadequate insufficient $ 185.13 documentation: No actual invoice Inadequate insufficient $ 555.38 documentation: No actual invoice $ 793.91 $ Page # Pg 160 Pg 161 Pg 161 15 Annexure A:Tax Summary CM/Subcontractor Description Hensel Phelps WA #002 - Construction Field Office Hensel Phelps WA #002 - Construction Field Office Hensel Phelps WA #002 - Construction Field Office Hensel Phelps Hensel Phelps Hensel Phelps Hensel Phelps Hensel Phelps Hensel Phelps Hensel Phelps Hensel Phelps Hensel Phelps Hensel Phelps Hensel Phelps Hensel Phelps VECA VECA VECA VECA VECA WA #002 - Construction Field Office WA #002 - Construction Field Office WA #016 - Construction Progress Cleaning WA #016 - Construction Progress Cleaning WA #017 Operational Safety WA #017 Operational Safety WA #017 Operational Safety WA #023 - Scaffold Protection WA #023 - Scaffold Protection WA #023 - Scaffold Protection WA #023 - Scaffold Protection WA #023 - Scaffold Protection WA #023 - Scaffold Protection WA #023 - Scaffold Protection WA #039 - Craft Bottled Water CONSUMABLES & SUPPLIES CONSUMABLES & SUPPLIES CONSUMABLES & SUPPLIES EQUIPMENT RENTALS EQUIPMENT RENTALS VECA EQUIPMENT RENTALS VECA EQUIPMENT RENTALS VECA EQUIPMENT RENTALS VECA INSTALLED WORK PROTECTION VECA LOGISTICS TRAILER RENTAL VECA VECA Hensel Phelps Hensel Phelps Sales Tax on Previously Billed Amount Sales Tax on Temporary Power Hensel Phelps Hensel Phelps Hensel Phelps Vendor Willscot Willscot CDW Direct $ $ $ Base 3,682.63 4,925.32 4,272.03 $ $ $ Tax amount 375.63 502.38 435.76 Best Buy Ace Normandy Invoice No 9025064142 9025060746 AH1MY7N #BBY01807108953343 I87323/7 $ $ 3,059.89 52.98 $ $ White Cap #50033849052 $ 672.92 #50034518409 #19RQ-NCYM-F4R7 #200822944 #201268021 #150169262-00 #1L9X-C7HY-D7MQ #1KFF-MFC3-4X47 #1XR3-F9KW-G1H6 #14NY-Q3JQ-FVLX #16MQ-XDPD-MCXT #19TG-RCDC-F1RY #1NDT-3D6M-GNRW 1493046 1493169 1493370 312584-8 313473A-8 $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 27927 White Cap Amazon Business Uline Uline Tacoma Screw Amazon Business Amazon Business Amazon Business Amazon Business Amazon Business Amazon Business Amazon Business PACIFIC INDUSTRIAL SUPPLY PACIFIC INDUSTRIAL SUPPLY PACIFIC INDUSTRIAL SUPPLY BIRCH EQUIPMENT BIRCH EQUIPMENT GEORGETOWN RENTAL EQUIPMENT BIRCH EQUIPMENT GEORGETOWN RENTAL EQUIPMENT EDGE CONSTRUCTION SUPPLY PACIFIC MOBILE STRUCTURES, INC Hensel Phelps Shinn Mechanical Amount Billed $ 4,058.26 $ 5,427.70 $ 4,707.79 Page # Pg 14 Pg 15-16 Pg 17 312.11 5.40 $ $ 3,372.00 58.38 Pg 18-24 Pg 25 $ 68.56 $ 741.48 Pg 40 3,902.68 202.88 641.26 48.43 872.14 132.99 25.95 12.34 23.99 14.89 46.98 239.00 71.08 141.73 63.97 1,215.25 1,375.29 $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 398.08 20.69 65.41 4.94 88.96 13.56 2.64 1.26 2.45 1.52 4.80 24.38 7.36 14.67 6.62 122.95 140.28 $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 4,300.76 223.57 706.67 53.37 961.10 146.55 28.59 13.60 26.44 16.41 51.78 263.38 78.44 156.40 70.59 1,338.20 1,515.57 Pg 42 Pg 44 Pg 45 Pg 46 Pg 52 Pg 53 Pg 54-55 Pg 56 Pg 57 Pg 58 Pg 59 Pg 75 Pg 117-118 Pg 119-120 Pg 121-122 Pg 124 Pg 127 $ 3,100.00 $ 316.20 $ 3,416.20 Pg 128 312584A-8 $ 848.86 $ 85.58 $ 934.44 Pg 129 27909 $ 9,250.00 $ 943.50 $ 10,193.50 Pg 130 $ 2,990.00 $ 304.98 $ 3,294.98 $ $ 4,483.00 45,717.31 4,940.29 50,380.48 42,835.00 1,109.39 136,030.18 457.29 4,663.17 2,708.59 4,412.01 92.72 16,604.45 $ $ $ $ $ $ $ $ $ $ $ $ $ $ 47,247.01 1,202.11 149,926.04 H27098 INV-00491236 Total Pg 156 Pg 157 Pg 131 Pg 163 Pg 62 Pg 78 16 Project Dashboard: SOV Digitization Description of Work Scheduled Value PA#4 Scheduled Value PA#5 Deviation Variance analysis: Schedule of Value Hensel Phelps $ 90,983,032.63 $ 92,037,202.63 $ 1,054,170.00 SC/CM - Daifuku $ 209,318,708.05 $ 209,318,708.05 $ - ECCM - VECA $ 97,445,008.36 $ 96,393,670.36 $ (1,051,338.00) Bid Subs $ 9,606,353.00 $ 9,606,353.00 $ - HPCC Fee (6.85%) $ 25,446,090.32 $ 25,443,258.32 $ (2,832.00) MACC Total $ 432,799,192.36 $ 432,799,192.36 $ - HPCC Fee (6.85%) Bid Subs ECCM - VECA SC/CM - Daifuku Hensel Phelps $- $50.00 $100.00 $150.00 $200.00 $250.00 Millions Scheduled Value PA#5 Scheduled Value PA#4 17 Subsytem Hensel Phelps Allowances Contingency Total Completed and % Complete Stored to Date $ 5,065,724.03 14.12% $ 634,202.80 2.60% $ 25,370,000.00 $ 167,156.83 0.66% $ 6,306,374.63 $ - 0.00% $ 44,170.00 $ 488.73 1.11% SC/CM - Daifuku $ 209,318,708.05 $ 4,158,971.66 1.99% ECCM - VECA $ 96,393,670.36 $ 8,254,634.47 8.56% Bid Subs $ 9,606,353.00 $ 317,688.00 3.31% Fee $ 23,769,164.76 $ 7,467,498.59 31.42% NSS Fee $ 1,674,093.56 $ 43,442.90 2.60% MACC Total $ 432,799,192.36 $ 26,109,808.01 6.03% Change Orders NSS Fee Fee Change Orders Hensel Phelps HPCC Fee (6.85%) Variance analysis: SOV to Completed & Stored through (PA#5) SC/CM ECCM - Bid Daifuku VECA Subs Description of Scheduled Value Work General Conditions $ 35,877,336.00 GCCM NSS $ 24,439,322.00 HPCC Fee (6.85%) Project Dashboard: Total Completed & Stored Contingency Allowances GCCM NSS General Conditions $- $40.00 $80.00 $120.00 $160.00 $200.00 $240.00 Millions Total Completed and Stored to Date Scheduled Value Value of Current Payment Application Value of Observations Total Value of Payment Applications Reviewed $ 2.978 Million $ 0.388 Million $ 26.109 Million 18 Project Dashboard : CM Fee Trend - Hensel Phelps Pay App # CM Fee Calculated (Cumulative) (Incl. Insurance & Bonds) CM Fee Billed (Cumulative) PA#1 PA#2 PA#3 $ 3,166,048.78 $ 7,052,505.64 $ 7,228,604.99 $ 7,361,559.94 $ 7,510,972.49 $ 3,166,048.78 $ 7,052,505.65 $ 7,232,466.03 $ 7,181,499.21 $ 7,510,941.49 Variance $ $ $ $ (180,060.73) $ (31.00) 0.00 0.01 PA#4 3,861.04 PA#5 Hensel Phelps - Fee Tracker $8,000,000.00 $7,228,604.99 $7,052,505.64 $7,232,466.03 $7,361,559.94 $7,510,972.49 $7,510,941.49 $7,181,499.21 $7,052,505.65 $6,000,000.00 $4,000,000.00 $3,166,048.78 $3,166,048.78 $2,000,000.00 PA#1 PA#2 Hensel Phelps CM Fee Calculated - Hensel PA#3 PA#4 PA#5 Hensel Phelps CM Fee Billed - Hensel 19 Project Dashboard : CM Fee Trend - VECA Pay App # CM Fee Calculated (Cumulative) (Incl. Insurance & Bonds) CM Fee Billed (Cumulative) Variance PA#1 PA#2 PA#3 PA#4 PA#5 $ 61,184.69 $ 115,815.10 $ 842,570.32 $ 1,002,889.98 $ 1,122,748.97 $ $ 61,184.68 (0.00) $ $ 115,815.09 (0.01) $ 842,570.32 $ (0.00) $ $ 998,206.61 (4,683.37) $ $ 1,118,065.59 (4,683.38) VECA- Fee Tracker $1,200,000.00 $1,122,748.97 $1,002,889.98 $1,118,065.59 $842,570.32 $998,206.61 $800,000.00 $842,570.32 $400,000.00 $61,184.69 $115,815.10 $115,815.09 $$61,184.68 PA#1 PA#2 VECA CM Fee Calculated - VECA PA#3 PA#4 PA#5 VECA CM Fee Billed - VECA 20 Our Path Forward  Fort Hill will begin the Payment Application #6 in end January 2025 December 2025 January 2026 Th Fr Sa Su Mo Tu We Th Fr Sa Su 4 5 6 7 29 30 31 1 2 3 4 10 11 12 13 14 5 6 7 8 9 10 11 16 17 18 19 20 21 12 13 14 15 16 17 18 22 23 24 25 26 27 28 19 20 21 22 23 24 25 29 30 31 26 27 28 29 30 31 Mo Tu 1 2 8 9 15 We Fort Hill Review Starts Issuance of Monthly Report Analysis and Reconciliation Note: The status of observations from previous audit (from payment application 1 to 4) will be tracked separately along with Construction Manager responses. 21 22