7. Work Group / Committee Reports. None.
8. Consent Agenda
It was moved and seconded (Keller/Marzano) to approve the consent agenda
consisting of:
A. Approve the January 6, 2026 minutes.
B. Approve disbursements totaling $2,378.61 to the State Auditor’s Office during the
period of December 22, 2025 through January 25, 2026.
C. Approve disbursements totaling $25,333,885.54 issued during the period
December 22, 2025 through January 25, 2026.
D. Authorize the CEO or his designee to execute the amended Interlocal Agreement
MOA 2023078 (Amend 001/13125) between the NWSA and National Oceanic
Atmospheric Administration’s (NOAA), National Ocean Service, Center for
Operational Oceanographic Products and Services, for the management,
operation, maintenance and repair of the NOAA’s Tacoma and Seattle PORTS®
RealTime Systems.
E. Approve amendment to contract 071686 to increase authorized amount by
$39,221.25 for a total authorized new amount of $394,221.25.
The motion carried by the following vote:
Port of Seattle Port of Tacoma
Ryan Calkins - aye Kristin Ang - aye
Fred Felleman - aye Deanna Keller - aye
Toshiko Hasegawa - aye Dick Marzano - aye
J.T. Wilcox - aye
(Commissioners Cho, McCarthy, Mohamed absent/excused)
9. Action
A. Terminal 7 (T7) Infrastructure Repairs and Improvements Design Authorization.
Bob Meyer, Director of Port Operations and Elly Bulega, Engineering Project
Manager II gave the presentation. Terminal 7 is located on the Sitcum Waterway
and is currently being used for autos, cargo, military, and overflow breakbulk roll-on
/ roll-off cargo. The wharf’s key elements (including the waterline, the pile caps,
bollards, pier sprinklers) are in poor condition and need to be repaired. Additionally,
the administrative building at the terminal, nearly 38 years old, requires repairs and
upgrades to achieve the desired additional 20 years of service life. This request is
for funding to complete the design to make the required improvements.