Project Risks
7
Risk Description Probability Impact Mitigation
Permit Delay Federal in-water permit review
and approval turnaround time;
unforeseen government
shutdown/resource constraints
Low Low
IAWP approved by Ecology. SEPA DNS and NWP-38
approval eta early October. Continued engagement with
federal/local agencies, tribes, etc. to ensure awareness
of project changes. Schedule buffer in permitted work
window to absorb unforeseen permit delays.
Discovery of
Discarded
Military
Munitions
(DMM)
DMM discovery during
construction will halt work until
notification to resume work is
issued.
Low Moderate
Low risk of encounter based on discovery data in
dredge area. Port to provide DMM training and safe
screening/disposal protocol for GC to implement if
DMM’s are found. Protocol will implement a
construction- and operation-free exclusion zone.
Contract Risk Existing MC-Unit Price Dredging
contract with single general
contractor (GC) will be shared
across multiple dredge projects.
Low Low
Proactive communication and coordination between
internal Port staff and GC to manage resource capacity
and phasing. Work Authorization negotiation in
progress.