
COMMISSION AGENDA – Action Item No. 8g Page 2 of 5
Meeting Date: October 27, 2026
Template revised June 27, 2019 (Diversity in Contracting).
on both port- and starboard sides, the maintenance dredge to -35’MLLW will also allow for
vessels to adjust their position at the dock to accommodate bollards, gangways, shell doors,
shore power connection, and all necessary points for operation.
The west cruise berth is located within the approximately 85-acre Sediment Cleanup Unit (SCU)
of the Terminal 91 Cleanup Site, which includes both an upland area and the submerged land
area. In addition to the west berth, the SCU also includes the central and eastern berths; these
areas will not be impacted by the proposed maintenance dredging. Under MTCA Agreed Order
No. DE24768, the Port is currently conducting additional field investigations to inform the
Feasibility Study for the submerged lands, which will evaluate cleanup alternatives. Per direction
to the Port from WA State Department of Ecology in September 2025, the proposed dredging in
the west berth is considered an Interim Action under the Agreed Order.
Diversity in Contracting
Construction will be performed by utilizing an existing Major Construction Unit Price contract for
dredging construction services. No WMBE aspirational goal will be established due to the low
availability of WMBE firms in the highly specialized dredging and disposal fields.
DETAILS
Scope of Work
The following tasks will be performed on this project:
(1) Dredge approximately 3,000 CY of sediment at the main & west channel to a
maintenance dredge elevation of -35’ MLLW and dispose upland at an approved facility.
(2) Fulfill all requirements of the Final Interim Action Work Plan approved by Ecology,
including post dredge sampling and laboratory analysis, and preparing an Interim Action
Completion Report.
Since the previous Commission Authorization, the project scope no longer includes dredging of
the high spots on the pier face and will proceed with the main dredge footprint only. This is the
result of the following two considerations:
(1) The project team worked closely with the T91 Cruise Shore Power Extension project team
due to the overlapping project footprint at the T91 west cruise berth. The teams
concluded that the berth face dredging scope would present critical schedule risk to
permanent shore power delivery at T91 West Cruise berth.
(2) Based on updated bathymetry survey data, it was determined that the high spots along
the berth face do not impact standard operation. High spots and topography changes at
the west cruise berth will be monitored for change through regular survey.
Given the minimal dredge quantity previously planned at the pier face, removal of this scope did
not result in substantive impacts to the project schedule or cost.