Item No. ___11a_supp ____ Date of Meeting: October 27, 2026_ Draft Plan of Finance 2027-2031 and Tax Levy Briefing October 27, 2026 Overview • Tax Levy • Draft Plan of Finance • Appendix 2 2027 Budget Process 2026 Budget Development (June-August) Budget Briefings (SeptemberOctober) Plan of Finance and Tax Levy Briefing Introduction & Public Hearing for 2027 Budget (October 27) (November 17) Adoption of 2027 Budget (November 23) Operating and Capital Budget Reviews roll-up into Plan of Finance and Port-wide Budget 3 Tax Levy Background and Update 2027 Preliminary Budget October 27, 2026 Managing the Levy Using a Balanced Approach GOAL Manage the levy to provide financial financial resilience and to support support the region, today and for for the long term RECOMMENDATION 2027 ACTIONS Move from 75/75 to 80/70 • Levy at 80% of the maximum maximum • Cap G.O. debt service at 70% of 70% of the annual levy Set the 2027 levy at $97.59M 5 Context of the Levy Discussion 2026 Levy Discussion • In the 2026 Tax Levy Discussion, the Commission charged Corporate Finance with examining multiple levy scenarios. March Retreat • Those scenarios were previewed at the March retreat, as well as a new approach for increasing capacity without increasing debt. Proposal • The new approach previewed in March is today's baseline staff proposal. 6 Levy Background: A Tool Managed with Discipline 1911 1961 King County voters State expands the create the Port as a Port's taxing public port district authority 2010 2015 2023 2027 Transportation & Infrastructure Fund created for regional commitments Commission sets levy use criteria for for capital (updated (updated 2018) Environmental Legacy Fund created; $62M deposited to date Proposed: 80/70 to fund resilience and revenue Throughout, the levy has funded projects that promote resiliency and community benefit: environmental cleanup, cleanup, community programs, regional transportation (including the SR-99 tunnel) and public waterfront assets. The waterfront assets. The Commission has chosen to keep it well below the legal maximum. 7 2026 2027 Est. 2025 2024 2023 2022 2021 2020 2019 2018 2017 $50 2016 2015 2014 2013 $75 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 $100 2002 2001 2000 1999 1998 1997 1996 1995 1994 1993 1992 1991 1990 Levy History $ Millions $125 Maximum Allowable Levy Actual Levy Levy Tied to Inflation (beginning 1990) $25 $0 8 A small share of the property tax bill 1.1% $87 $90.2M of the $8.5B in King County property property taxes went to the Port in in 2026 Port share of a median homeowner's homeowner's $8,204 total property property tax bill (2026) 2026 levy: 75% of the $120.2M maximum; up 2.0% from $88.4M Because assessed value grew faster than the levy in 2026 (~3.5% vs. 2.0%), the millage rate edged down, from $0.1012 to $0.0980 per $1,000. 9 Two levers set how the levy is used Lever 1 · How much we levy A percentage of the statutory maximum. The gap below below the maximum is "dry powder" for future needs. needs. Lever 2 · How much we leverage The share of the levy committed to G.O. bond debt debt service. The rest is cash for capital and programs. programs. THE RULES • Commission sets the levy each year, up to the legal maximum • The maximum grows about 2% a year (1% limit plus new construction); 2027 max ≈ $122.0M • Usable for any Port purpose except revenue bond debt service • G.O. bond debt service is the first claim on the levy • Commission can further restrict uses by policy 10 The levy punches above its weight Direct value to the region Indirect value: our credit • Legacy environmental cleanup: Duwamish, T-108, T-25, T-115 • Community programs, about $13M a year • Regional transportation, including SR-99 • Public waterfront capital investments • Levy net of G.O. debt service boosts revenue bond coverage • Diversifies revenue beyond airport and maritime business • Rating agencies cite "prudent management of the tax levy, including maintaining a cushion" Up to $25M Added debt service from a credit downgrade (5-25 bp) on the new airport debt planned from 2027-2031 11 Our needs are outpacing the current approach Infrastructure upgrades & modernization Aging and at-risk assets Mission opportunities • T-91 Electrical System Modernization • Updating Infrastructure for Future fuels • Waterfront Clean Energy Strategy Implementation • Enhancing Infrastructure Resiliency • Seismic upgrades • Pier 69 renewal • Mooring dolphins • FT North West Dock • Salmon Bay Investments • Bulkhead replacements • Habitat acquisition • Real Estate Acquisition • Financial sustainability projects • Needs beyond 2031, when capital plans assume lower spending 12 From 75/75 to 80/70: more cash, not more debt 2027, at the ~ $122.0M m axim um C urrent 75/75 Pro p o sed 80/70 C hang e 75% 80% + 5 p ts Levy am o unt $91.5M $97.6M + $6.1M H ead ro o m b elo w m axim um $30.5M $24.4M G .O . d eb t service cap (75% vs. 70% ) $68.6M $68.3M −$6.1M Levy cash after m axim um G .O . d eb t service $22.9M $29.3M Levy as % of m axim um −$0.3M + $6.4M Debt capacity stays flat. The proportion of our capital funded with cash increases, mitigating growth in interest costs. 13 The Step Today: 80/70 O p tio n Taxpayer lens Investo r lens A d d ed capacity C urrent 75/75 M o d est annual increases; fund s key initiatives Flexib ility fro m m anag ing levy and leverag e Baseline Pro p o sed 80/70 M o d erate increase; value d ep end s o n use Flexib ility m aintained thro ug h levy and leverag e lim its $67M , 2027-2035 Because the levy base grows each year, the added capacity compounds, while the cushion below the maximum stays in place. The Long-Term Commitment Hold the Levy at this level and shape the capital plan to accommodate. 14 What it means for a typical homeowner 2026 PORT TAX 2027 Proposal (ESTIMATE) $87 ≈$95 median home, levy $90.2M median home, levy $97.59M +$8 a year About 67¢ a month. The levy rises rises 8.2% in 2027, then returns returns to ~2% annual growth growth with the maximum Estimate assumes the median home's assessed value moves with the countywide total. Based on the preliminary assessed value the estimated median home price for 2027 is $850,000. 15 The credit strengths investors value stay intact Governance Cushion kept Less leverage Commission policy and use criteria still direct every levy dollar 20% of capacity, about $24M a year, stays untapped G.O. debt service cap More levy net of G.O. debt tightens from 75% to 70% service supports revenue of the levy bond coverage Coverage up up 16 Sources of Tax Levy & Related Funding: 2027-2031 Total Sources - $904M  2027 levy set at 80% of maximum allowable  Future tax levy collections based on ~2% annual levy growth  $78M of existing GO Bond proceeds from issuances in 2022 and 2024  Forecasts assume $250M of additional GO Bonds issue over the next 5 years to support capital investments and environmental costs Note: Excludes TIF funds 17 Uses of Tax Levy & Related Funding: 2027-2031 Total Uses - $904M  Existing GO Bonds DS includes both Seaport capital investments and SR-99 tunnel contribution  Environmental costs are projected to continue well past 2031, but are fully funded with levy resources including G.O. bonds  Assumes continuation of levy funded Community Programs at ~$13M annually Note: Excludes TIF spending Every Additional Use of the Tax Levy for Operations Has an Opportunity Cost, Reducing Maritime Capital 18 Managing the Levy Using a Balanced Approach GOAL RECOMMENDATION 2027 ACTIONS Manage the levy to provide financial resilience and support the support the region, today and for for the long term Move from 75/75 to 80/70 • Levy at 80% of the maximum maximum • Cap G.O. debt service at 70% of 70% of the annual levy Set the 2027 levy at $97.59M 20 Draft Plan of Finance 2027-2031 2027 Preliminary Budget October 27, 2026 The Draft Plan of Finance The Draft Plan of Finance is a funding plan for the Port's five-year Capital Improvement Program (CIP) • A tool for the Commission to inform the budget process and long-term capital investment decisions • Flexible tool that is updated as circumstances change • Plan is developed based on a sustainable financial model • An important tool for investors • Gauge the future financial health of the Port • Provides insight into Port's approach to financial stewardship 22 Funding Resiliency • Establish financial guardrails to manage uncertainty • Provides a cushion for income variability Airport Seaport Minimum Revenue Bond Debt Service Coverage 1.40x (1) 1.80x Minimum Fund Balance 18 months 12 months (1) Calculation for rates and charges may differ from the calculation for bond compliance 23 Seaport Capital Spending (2027-2031) • Maritime $682M - 44% in design or construction - $50M (7% of CIP) reserves • NWSA $353M includes - Port's 50% share of NWSA CIP $263M - Projects related to NWSA $90M • 2026-2030 CIP was $961 million • Stormwater Utility is self-funded and not included in the Draft Plan of Finance 24 Seaport Capital Funding (2027-2031) • 62% of funding from operating sources: - Includes cash funding and revenue bonds paid from operating cash - Decrease in existing revenue bond debt service provides funding capacity • 30% is from tax levy related sources: - Tax levy cash - G.O. bonds paid by the tax levy • 7% from other sources including grants and Harbor Maintenance Tax (HMT)/WRDA - Funding sources limited to eligible projects 25 Airport Capital Spending (2027-2031) • Airport is a self-supporting enterprise • 78% in design or construction • $213M (5.1% of CIP) in reserves for unanticipated needs 26 Airport Capital Funding (2027-2031) • 93% funded from operating cash flow and revenue bonds • $273M capital grants (AIP, AIG, ATP) - S Concourse Evolution, Noise insulation projects, airfield pavement, others • Other funding includes: - Customer Facility Charges after the payment of CFC eligible debt service • Most PFC's are used to pay revenue bond debt service; remaining PFCs are available to cash fund capital 27 Port-wide Revenue Bond Debt Service Coverage Forecast • Represents all net income of the Port (including Airport and Seaport) divided by all revenue bond debt service • Tax levy after payment of G.O. bond debt service adds to coverage • Coverage informs debt and capital management and provides a measure of financial sustainability and is critical to investors and rating agencies • Decreasing Port-wide DS coverage is driven by large Airport capital spending but is consistent with the Port's strong credit rating 28 2026 Finance Accomplishments  Refresh of the Port's Subordinate Lien - Adoption of Master Resolution and amendment of (2) Series Resolutions  Extension of LOC supporting the Ports 2008 Variable Rate Demand Bonds (VRDBs)  2026 First & Intermediate Lien Revenue Refunding Bonds - Par Value: $251.9 million; resulted in $16.4 million of NPV debt service savings  2026A Subordinate Lien Revenue Bonds (VRDBs) - Par Value: $225 million; proceeds used to fund Airport CIP  2026B Subordinate Lien Revenue Bonds (Direct Bank Loan) - Par Value: $120 million; proceeds used to pay off outstanding commercial paper 29 2027 Finance Initiatives • Issue revenue bonds to continue funding Airport CIP • Monitor need for new G.O. bonds to support Seaport capital needs • Monitor opportunities to refund debt for interest savings - Port has outstanding Revenue and G.O. Bonds that will be callable in 2027 - Refunding subject to market conditions and achieving Port debt service savings targets per policy • Renewal or replacement of expiring letter of credit 30 Increasing Financial Capacity for the Port of the Future • Operating Expenses - continue efforts to reduce growth • Operating Revenues - explore opportunities to generate revenues (without significant capital investments) • Capital Development - review prioritization and delivery methods • Financial Management - maintain strong credit and cost-effective debt issuance - ensure rigorous evaluation of investments 31 2027 Budget Process: Next Steps 2026 Budget Development (June-August) Budget Briefings (SeptemberOctober) Plan of Finance and Tax Levy Briefing Introduction & Public Hearing for 2027 Budget (October 27) (November 17) Adoption of 2027 Budget (November 23) Operating and Capital Budget Reviews roll-up into Plan of Finance and Port-wide Budget 32 Appendix 2027 Preliminary Budget October 27, 2026 Contents Pages 35 Additional Tax Levy Information 54 Industrial Development District Levy & Tax Increment Financing Information 59 POF Support: Airport and Seaport CIP and Funding 61 Credit Ratings 34 Port's Taxing Authority Port taxing limitations: Port is limited by the most restrictive - currently the 1% limit • 1% limit - The maximum levy is increased each year by the 1% limit factor - Prior year's maximum is increased by the lessor of 1% or inflation - New construction is added - The maximum levy for 2027 is estimated to be ~$122.0 million • 45 cent limit - The amount of the tax levy in any given year is limited to 45 cents per $1000 of assessed value - For 2026, this limit would translate to ~$395.0 million - Excludes the amount needed to pay G.O. bond debt service 35 Levy Policies and Practices - 2027 Update • Manage General Obligation (G.O.) debt service to no more than 70% of the annual levy - Prior practice was limit G.O. debt service to 75% of annual levy • Capital investment criteria • Pay for legacy environmental costs • Limited Airport use - costs ineligible for Airport funding per FAA • Retain tax levy flexibility - levy below the statutory maximum - 2026 levy at 75% of the maximum; 2027 recommendation at 80% of the maximum - The difference between the actual levy and the maximum reserves "dry powder" for future resiliency - Supports Port's strong credit ratings 36 Optimizing Financial Flexibility - A Range of Options that Balance the two Levers of Flexibility Leverage (% levy used to pay G.O. Bonds) 40 60 80 100 % of Maximum Levy 100 90 80 70 60 37 Tax Levy Use Criteria for Capital Investments Uses: Commission established in 2015; updated in 2018 Operating Cash Tax Levy Business income sufficient to support investments Economic benefit Strategic Initiatives Short payback/ Self funding No or long payback Location South Harbor North Harbor Asset Renewal 38 2016-2027 Tax Levy & Millage Rate (1) (1) Millage rate represents the amount per every $1,000 of assessed valuation 39 Taxpayer Impact 2026 2027 preliminary Tax Levy ($ million) 90.2 97.6 Estimated millage rate ($/1000) 0.0980 0.1112 Median home value ($) (1)(2) 887,000 850,000 $87 $95 Estimated median home Port tax ($) (1) (2) 2026 per King County; 2027 data is not yet available 2025 median assessed value was $844,000 • The Port's levy was approximately 1.1% of total property taxes levied in King County in 2026 40 Overall Taxpayer Impact - 2026 • Of the $8.5 billion of property taxes paid in King County, about 1.1% goes to the Port • In 2026, the median homeowner paid $8,204 in total property tax with $87 going to the Port 41 Tax Levy & Related Funds • In addition to the tax levy fund, the Commission has established other related funds that are funded by the tax levy • These funds are restricted by Port policy, not law, and currently include: - Environmental Legacy Fund (ELF) - established in 2023 to provide funding for legacy environmental liabilities. Will be used in combination with G.O. Bonds - Transportation & Infrastructure Fund (TIF) - established in 2010 to provide funding for the Port's various regional transportation commitments. TIF is a stand-alone fund that fully funds current obligations • The Port is also able to issue General Obligation (G.O. Bonds). The proceeds of the bond sale can be used in lieu of levy cash - GO Bond debt service is paid from tax levy fund 42 Transportation and Infrastructure Fund (TIF) TIF ($ million) Beginning Balance Transportation Investments Ending Balance Transportation Investments ($ million) Seattle Heavy Haul Network Fast Corridor II Safe and Swift Puget Sound Gateway (SR 509) TOTAL 2027 $ $ 2.5 $ 1.5 15.0 19.0 $ 2027-2031 Post 2031 $ 45.7 $ 17.9 (27.8) (4.0) 17.9 13.9 2028 2029 2.0 $ 0.8 2.8 $ 2030 2.0 $ 2.0 $ 2031 2.0 $ 2.0 $ 2027-2031 2.0 $ 2.0 $ Post 2031 10.5 $ 0.8 1.5 15.0 27.8 $ 4.0 4.0 TIF has provided funding for other regional transportation efforts, including: • West Seattle Bridge • FAST Corridor I • South Park Bridge • East Marginal Way Grade Separation 43 Environmental Legacy Fund (ELF) ELF ($ million) Beginning Balance Additional Contribution (1) Environmental Remediation Liabilities Environmental Grant Receipts (2) Ending Balance 2027-2031 Post 2031 $ 31.2 $ (34.9) (8.0) 3.7 8.0 - • ELF was established in 2023 to provide funding for legacy environmental liabilities • Funded an estimated $50.7 million of Seaport environmental remediation efforts through 2026 (including 2026 forecast) • Environmental efforts include, but are not limited to: • Lower Duwamish Superfund • T-108 Chiyoda site • Terminal 25 South • Terminal 115 (Boeing Plant 1) (1) (2) No contribution currently assumed for 2027. Additional contributions will be reviewed on an annual basis. Does not represent all assumed environmental costs during the forecast period. Additional environmental liabilities assumed to be funded with tax levy fund upon depletion of ELF. 44 Tax Levy Sub Fund Balances Established by the Commission to Prepare for Future Obligations Millions Millions * For future commitments, currently forecast at $4M 45 Environmental Spending * Based on known liabilities only. Includes spending from tax levy, ELF and G.O. bond proceeds (if needed). Additional environmental remediation spending is expected beyond 2031 46 2027 Port Community Program Funding by Activity Economic Development • • • • Diversity in Contracting -$2.4M Tourism Marketing Support - $2.1M EDD Partnership Grants - $950K Maritime Blue - $100K Workforce Development * 2027 Proposed Budget: $19.6M • Workforce Development Department - $5.0M • High School Interns - $550K Equity, Diversity & Inclusion • • • • • OEDI Department - $4.4M South King and Port Communities Fund - $2.6M Friends of the Waterfront- $750K Staff Costs supporting DVCEP & SKCCIF - $776K Duwamish Community Equity program (DVCEP) - $627K • $1.4M SeaTac Community Relief * Detailed list continued on next slides 47 2027 Proposed Community Programs 2027 Proposed Budget 2,648 627 950 2,124 1,400 100 5,018 550 2,388 4,404 750 % of the 2027 2027 Budget Funded Funded by the levy by the levy 2,648 100.0% 627 100.0% 950 100.0% 870 41.0% 0.0% 1,400 100.0% 100 100.0% 3,873 77.2% 299 54.4% 300 12.6% 2,127 48.3% 750 100.0% 2024 Budget 2,214 471 950 1,875 466 1,400 175 5,077 486 2,304 2,065 2025 Budget 2,205 619 950 2,154 518 1,400 175 4,976 520 2,356 2,459 750 2026 Revised Budget 2,195 617 950 2,134 518 1,400 180 4,972 523 2,463 2,540 2,000 Sub Total 18,803 19,591 20,642 18,811 11,796 63% Payroll charged to the Levy 4 Grand Total 589 19,392 781 20,372 848 21,491 776 19,587 776 12,572 100.0% 64.2% Program (in $000) 1) South King and Port Communities Fund 1 2) Duwamish Valley Community Equity Program 3) EDD Partnership Grants 4) Tourism Marketing Support Program 5) Airport Spotlight Ad Program* 6) City of SeaTac Community Relief* 7) Maritime Blue (formerly Maritime Innovation Center) 8) Workforce Development 9) High School Internship Program 2 10) Diversity in Contracting 11) Equity, Diversity & Inclusion 3 12) Friends of the waterfront Notes: 1) SKPC budgeted under Ext Rel, EDI, and DIC 2) $250K Small Business Accelerator under DIC is part of item 1 SKPC 3) $1.9M for Economic Opportunities for Communities (EOC) under EDI is part of item 1 SKPC 4) 2027 Payroll only for CPO & Ext. Rel. Other payroll from HS Interns, WFD, EDI are included in the individual items above * Non-Operating Accounts 48 Community Programs Funded by Tax Levy Program (in $000) 1) South King and Port Communities Fund 1 2) Duwamish Valley Community Equity Program 3) EDD Partnership Grants 4) City of SeaTac Community Relief* 5) Maritime Blue (formerly Maritime Innovation Center) 6) Workforce Development 7) High School Internship Program 2 8) Diversity in Contracting 9) Equity, Diversity & Inclusion 3 10) Friends of the waterfront 11) Other Total Payroll charged to the Levy 4 Grand Total 2024 Funded by the levy 2025 Funded by the levy 2026 Funded by the levy 2027 Funded by the levy Inc/(Dec) from 2026 Revised Budget $ Change % Change 2,214 471 950 1,400 175 3,863 259 300 203 806 11,772 2,205 619 950 1,400 175 3,762 280 310 226 750 1,608 12,404 2,195 617 950 1,400 180 3,827 290 300 230 2,000 1,438 13,577 2,648 627 950 1,400 100 3,873 299 300 2,127 750 870 11,796 453 10 (80) 46 9 1,897 (1,250) (568) (1,781) 17.1% 1.6% 0.0% 0.0% -80.0% 1.2% 3.0% 0.0% 89.2% -166.7% -65.3% -15.1% 580 12,352 781 13,185 848 14,426 776 12,572 (72) (1,854) -9.3% -14.7% Notes: 1) SKPC budgeted under Ext Rel, EDI, and DIC 2) $250K Small Business Accelerator under DIC is part of item 1 SKPC 3) $1.9M for Economic Opportunities for Communities (EOC) is part of item 1 SKPC 4) 2027 Payroll only for CPO & Ext. Rel. Other payroll from HS Interns, WFD, EDI are included in the individual items above * Non-Operating Accounts 49 Major Capital Projects Funded with Levy/G.O. bonds • T91 Berths 6&8 redevelopment and dock rehabilitation • T91 Uplands development • Fishermen's Terminal - docks, buildings and site improvements Funding flexibility supports financial resilience - Projects may be funded with either tax levy or G.O. bonds depending on funding availability - Future funding availability may result in some projects being funded with the General Fund or Revenue Bonds • East and West Waterway deepening • NWSA North Harbor projects - 50% share 50 2026 Tax Levy Fund Sources and Uses ($ million) SOURCES OF TAX LEVY FUNDS 2026 Beginning Levy Fund Balance Annual Tax Levy Investment Income Total Sources 2026 $ 25.0 90.2 0.7 $ 115.9 USES OF TAX LEVY FUNDS G.O. bond debt service (existing) Community Investments Seaport Capital Investments Transfer to ELF Aviation NOISE Other Total Uses $ Projected Ending 2026 Levy Fund Balance $ 38.9 15.2 14.3 5.0 4.0 0.4 77.8 $ 38.1 Note: Excludes ELF and TIF 51 5-year Tax Levy Fund Sources and Uses ($ million) SOURCES OF TAX LEVY & RELATED FUNDS Beginning Balance - Tax Levy Beginning Balance - ELF Tax Levy Collections Existing GO Bond Proceeds Future GO Bond Proceeds Environmental Grant Receipts Total Sources 2027-2031 $ 38 31 502 78 250 4 $ 903 USES OF TAX LEVY & RELATED FUNDS G.O. Bond Debt Service (existing) G.O. Bond Debt Service (new) Environmental Remediation Liability (Non-Airport) Seaport Capital Investments Sound Insulation Community Programs Total Uses 2027-2031 $ 180 73 263 318 7 63 $ 904 Note: Excludes TIF 52 Airport and Seaport Benefit from the Tax Levy Airport Seaport Certain Noise Mitigation Projects* Legacy Environmental Remediation City of Seatac Safety Payment under ILA (expires 2027) Capital Investments (including G.O. Bonds) Tourism Tourism Certain Community Programs Certain Community Programs Public Expense/Transportation Project Public Expense/Transportation Project Supports Revenue Bond Debt Service Coverage Supports Revenue Bond Debt Service Coverage * Includes Sound Insulation Repair and Replacement Pilot Program & Highline School District NOISE spending not eligible for airport funding 53 IDD Levy - Background • Port can levy property tax within an Industrial Development District (IDD) - In addition to regular property tax - A port can form multiple districts • Coextensive with port district, or • Smaller area within the Port district - The Port already has two Industrial Development Districts • Port can implement the levy twice - Port of Seattle implemented first round in 1963 • Purpose is to provide for harbor improvements or industrial development of marginal lands - Broadly defined - Includes areas of poor planning or declining tax receipts 54 IDD Levy - Implementation • Port may implement a second round based on a new formula - Maximum of ~$2.4 billion over a period of up to 20 years • Average amount = ~$125 million (for 20 years) - Port can establish a smaller IDD or collect a lesser amount, but cannot bank the unused capacity • Process to implement - Publish notice by April 1 to begin collecting the next year - If within 90 days, a petition of 8% of voters (voting in the most recent gubernatorial election) opposes, the Port must hold a special election to approve the levy 55 IDD Levy Information: "Marginal lands" are defined to include property subject to the following (RCW 53.25.030) conditions: 1. An economic dislocation, deterioration, or disuse resulting from faulty planning. 2. The subdividing and sale of lots of irregular form and shape and inadequate size for proper usefulness and development. 3. The laying out of lots in disregard of the contours and other physical characteristics of the ground and surrounding conditions. 4. The existence of inadequate streets, open spaces and utilities. 5. The existence of lots or other areas which are subject to being submerged by water. 6. By a prevalence of depreciated values, impaired investments, and social and economic maladjustment to such an extent that the capacity to pay taxes is reduced and tax receipts are inadequate for the cost of public services rendered. 7. In some parts of marginal lands, a growing or total lack of proper utilization of areas, resulting in a stagnant and unproductive condition of land potentially useful and valuable for contributing to the public health, safety and welfare. 8. In other parts of marginal lands, a loss of population and reduction of proper utilization of the area, resulting in its further deterioration and added costs to the taxpayer for the creation of new public facilities and services elsewhere. 9. Property of an assessed valuation of insufficient amount to permit the establishment of a local improvement district for the construction and installation of streets, walks, sewers, water and other utilities. 10. Lands within an industrial area which are not devoted to industrial use but which are necessary to industrial development within the industrial area. 56 Tax Increment Financing • RCW 39.114 allows certain jurisdictions to form Tax Increment Areas (TIA) • Maximum area is $200 million of assessed value • Port taxes on any increase in assessed value goes to the TIA and not to the Port • Approximately 40 jurisdictions can form TIAs within the Port's boundaries • There are currently four active TIAs within King County • City of Bellevue formed TIA in 2026 - Legislature increased maximum assessed value to $500 million Impact on Port Tax Levy Year 2024 2025 2026 Port Tax Levy Diverted to TIAs ($) 5,537.98 5,893.00 11,232.79 Total 22,663.77 57 Managing for a Successful Port of the Future • • • • • • Risks to the Plan Mitigations Business disruptions - pandemic, recession Regulatory and legal requirements Federal funding uncertainty Aging infrastructure and unanticipated investments Limited flexibility to the CIP Looking beyond 2031 - Airport and Seaport capital plans assume lower spending levels • Conservative budgeting provides upside potential • Continued Demand for Airport and Cruise businesses • Greater Cost certainty - Environmental Liabilities are being settled - Airport mega projects are being completed • Resilient financial metrics • Begin efforts to increase capital capacity • HMT Risk of over-optimism is greater than the risk of pessimism 58 Seaport CIP and Funding Seaport CIP Maritime $ NWSA - 50% Share (North & South Harbor) NWSA - Reserve & Port Projects (1) Total $ Allocated Central Services CIP Total Seaport Funded CIP $ 2027-2031 ($ million) 681.9 263.4 90.3 1,035.6 13.8 1,049.4 (1) Includes N. Harbor channel deepening and other 100% Port legacy costs in N. Harbor. Note: totals may not add due to rounding 2027-2031 ($ million) Seaport Funding Sources Operating Cash (1) Grants Harbor Maintenance Tax (HMT) Tax Levy & Future GO Bond Proceeds (2) Existing G.O. bond proceeds Future revenue bond proceeds Total Seaport Funded CIP $ $ 469.2 26.7 50.2 240.0 78.5 184.8 1,049.4 (1) Includes non-airport income available after payment of revenue bond debt service. (2) Annual levy forecasted at 80% of the Port's maximum annual allowable levy. Note: totals may not add due to rounding 59 Airport CIP and Funding 2027-2031 ($ million) Airport CIP S Concourse Evolution Baggage Optimization 2026-2030 AFLD PVMNTS Main Terminal Improvement SEA Gateway C Concourse Expansion Other Capital Projects SAMP Preliminary Planning/Design(1) Proposed New Projects CIP Reserves TOTAL Allocated Central Services CIP Total Airport Funded CIP $ $ $ 1,579.4 449.0 353.2 195.8 35.1 9.5 782.9 161.9 308.4 213.2 4,088.4 59.5 4,147.9 2027-2031 ($ million) Airport Funding Sources Future revenue bond proceeds Operating Cash (1) Grants Existing revenue bond proceeds Customer Facility Charge (CFC) Total Airport Funded CIP $ $ 2,870.6 803.0 273.4 183.3 17.7 4,147.9 (1) Includes airport income available after payment of revenue bond debt service. Note: totals may not add due to rounding (1) Sustainable Airport Master Plan Note: totals may not add due to rounding 60 Current Credit Ratings General Obligation Bonds First Lien Revenue Bonds Intermediate Lien Revenue Bonds Subordinate Lien Revenue Bonds Fuel Hydrant Special Facility Bonds Fitch AAAA AAAA- Moody's Aaa Aa2 Aa3 A1 A1 S&P AA AA AAAAA+ Noted Credit Strengths: • Diverse asset and revenue base • Airport's market position and enplanement levels • Strong balance-sheet liquidity levels • Conservative debt structure and healthy debt service coverage ratios • Prudent management of the Tax levy including maintaining a cushion • Strong governance and management • Long-range strategic and sustainability plans • Vibrant and resilient area economy 61