Item No. 8c supp Meeting Date: Sept. 22, 2026 Terminal 25 South Cleanup Authorization for Removal Design/Removal Action Order with EPA September 22, 2026 1 Project Site: T25 South • Unique, very high ecological value in saltwater transition zone • Three related projects, one mobilization: - Upland cleanup required by EPA - Sediments cleanup required as East Waterway "Early Action" pursuant to EPA interim record of decision (IROD) - 10-acre habitat restoration 2 Soil & Sediment Cleanup • Cleanup must satisfy EPA • In-water cleanup treated as East Waterway "early action," must meet IROD • Upland cleanup to remove historical PCB hotspot discovered in 2019 • Estimated cost for cleanup (full removal) - Sediments Cleanup:$61 M - Upland Cleanup: $71 M • Habitat design and construction will be integrated with the cleanup 3 Key Schedule Milestones Field Investigation/Data Approval EPA EE/CA Approval/Action Memo GC/CM Solicitation EPA Design and Action Order 30% Design to EPA GC/CM Contractor Inclusion 60% Design to EPA 90% Design to EPA 100% Design & Permitting Construction Q1 2025 (complete) Q3 2026 (complete) Q3 2026 (complete) Q3 2026 (This Item) Q1 2027 Q1 2027 Q3 2027 Q1 2028 Q3 2028 Q1 2029 - Q2 2031 4 QUESTIONS? 1936 2026 2031 5 Habitat Restoration Restores 10 acres to fully functioning riparian, marsh, intertidal, and subtidal habitat: • Install substrates, vegetation, anchored wood, cobble, and intertidal channels • Green stormwater infrastructure to protect site from runoff from adjacent NWSA site • Public access not permitted, but site contributes to viewshed and popular fishing area 6