COMMISSION AGENDA – Action Item No. 8c Page 2 of 5
Meeting Date: September 22, 2026
Template revised June 27, 2019 (Diversity in Contracting).
BACKGROUND
Terminal 25 is located along the East Waterway. The northern two thirds of the property is an
active cargo facility, whereas the southern third of the property, known as T-25S, is an
underutilized parcel that has primarily been used in recent years for bulk material storage,
viaduct demolition material storage, and drayage parking. The eastern half of T-25S is licensed to
the Northwest Seaport Alliance (NWSA), and the western half of the site, managed by the Port
of Seattle (Port), has been identified as a future habitat restoration site.
The Port discovered a PCB hotspot at the T-25S site in 2020. An environmental investigation was
performed with EPA’s oversight, to refine the nature and extent of contamination and ensure
that the proposed habitat restoration meets EPA cleanup requirements for the East Waterway
Superfund site. This investigation was completed with the submittal of the final Engineering
Evaluation and Cost Analysis (EE/CA) on June 26, 2026. The cleanup alternative and cost
estimates were presented in the EE/CA. EPA selected and memorialized their preferred
alternative in their Action Memorandum issued June 24, 2026. The next phase of the cleanup
process is to perform the removal design and a removal action, which is the subject of this
Commission authorization request.
Although funding is not included for this request, the cost to complete the removal design and
removal action is currently estimated to be $132 million. Current year funding for this work was
included in the 2026 Environmental Remediation Liability (ERL) Program authorization, which is
funded through the Environmental Liability Fund (ELF) via the tax levy. Additional Funding
authorization will be proposed in subsequent annual ERL authorizations. The $132 million is
already identified in the Port’s 5-year and long-term ERL plans.
JUSTIFICATION
The Administrative Settlement Agreement and Order on Consent (ASAOC or “EPA Order”) is a
binding agreement to perform work by the Port; therefore, the signing of the EPA Order requires
Commission authorization. The project will formally initiate the process of removal design and
removal action for T25S, as necessary and required, to meet EPA’s cleanup objectives in its Action
Memorandum. By cleaning up the site, the Port advances the long-term protection of human
health and the environment, reduces our environmental liability, and enables the advancement
of future habitat restoration at the site.
Diversity in Contracting
The removal design effort will utilize consultant services via existing environmental IDIQ
contracts developed to serve design and permitting efforts such as those required by this
program. The Maritime Environmental Site Management IDIQ contract and Maritime