3rd Floor GT Booth Completion Funding
Item No.
8e_supp
Date of Meeting September 9, 2026
Project Location, Purpose and Scope
Location: Ground Transportation Center (3
rd
Floor SEA Main
Parking Garage)
Purpose:
To renovate and expand the existing facility to support
ground transportation operations
Scope:
Expansion of administration space including a staff
breakroom and restroom meeting accessibility requirements
2
Current Budget: $5,000,000
This Request: $400,000
Revised Budget: $5,400,000
The request supports the Port’s
obligations for construction
completion and closeout
The project is funded by the
Airport Development Fund
Schedule Milestones:
• Contract Executed July 2025
• Notice to Proceed October 2025
• Substantial Completion July 2026
Construction schedule extended
three months
Anticipate project completion by
Q4 2026 and closeout by Q3 2027
Project Budget and Schedule
3
Project Photos
4
Action Requested
Request Commission authorization for the Executive Director to
authorize an additional $400,000 to complete the 3
rd
Floor
Ground Transportation Booth Enhancements project at Seattle-
Tacoma International Airport (SEA).
This request increases the total authorization amount from
$5,000,000 to $5,400,000.