COMMISSION AGENDA – Action Item No. 8k Page 2 of 7
Meeting Date: August 11, 2026
Template revised June 27, 2019 (Diversity in Contracting).
County regarding the implementation schedule require the Port to demonstrate progress
towards the implementation measures necessary to meet the new permit limits.
The amount of this request is $41,200,000 to complete the full Architecture and Engineering
(A&E) design of the IWTP Program (CIP C801234), long-lead equipment purchases, and
completing early works packages. The total estimated project cost is currently $ 280,782,000.
Staff will return to the Commission following the completion of the 90% design and negotiation
for the Maximum Allowable Construction Cost (MACC), at that time staff will provide an updated
project cost estimate and request authorization to move forward with the full construction
package.
JUSTIFICATION
Since 2007, the IWTP has discharged industrial wastewater runoff containing aircraft deicers to
the King County Wastewater Treatment System. Through each permit cycle, King County has
restricted discharges because under sustained heavy aircraft deicer loads, the performance of
the County’s treatment plant has been disrupted by the Port’s discharges.
Over the past five years, the Port has evaluated technologies and methods to reduce impacts to
the King County treatment plant. This evaluation included a comprehensive assessment of
deicing source control, storage, and treatment technologies. This assessment resulted in
measures to reduce the amount of aircraft deicer applied and implemented operational
efficiencies. For example, most of the aircraft deicer applicators switched to an application
technology reducing the amount of deicer applied. This source reduction reduces the amount of
future storage needed.
Under the terms of the July 2021 and July 2026 Industrial Waste Discharge (IWD) permits, the
Port is required to implement infrastructure and operational modifications by 2031 to comply
with future discharge limits. The previous BOD mass loading limit of 60,000 lb./day will be
reduced to 15,000 lb./day maximum daily and 12,000 lb./day on a monthly average basis during
the 2031 permit issuance, with interim limits imposed in the 2026 permit cycle. The IWTP
modifications needed to comply with these reduced limits include significant additions to the
system for storage and pretreatment of IWS stormwater containing spent aircraft deicing fluid.
The 2026 IWD permit also includes a compliance schedule over the next five years to reflect
progress toward implementation of measures to meet further reduced 2031 effluent limitations.
The Port will continue to collaborate with King County Industrial Waste Program to meet permit
limits during construction of the project.
While the Port has developed a preliminary design of the pretreatment and storage systems,
some elements of the design scope present risks to overall cost and schedule (phasing, controls
architecture, storage requirements, seasonal modeling, etc.).
Diversity in Contracting
There will be a 15% WMBE aspirational goal associated with this contract from the designers.
The construction determination will be made at the 60% set.