Item No. Date of Meeting Terminal Envelope Upgrade - Roof Replacement Project August 11, 2026 Commission Meeting 8f_supp August 11, 2026 Project Purpose & Objectives • Water intrusion and surface damage has been observed at the airport terminal central zone • Project will replace the roofing system to: o Prevent damage to the building underlying structural elements o Preserve the quality of the environment for people working in the space below 2 Project Location Project scope zone highlighted in yellow 3 Schedule Overview Delivery Method: Major Works: Design-Bid-Build 4 Action Requested • Request single authorization for $6,685,000 for the Executive Director to take all steps necessary to complete the project • Estimated total project cost is $7,585,000 (design to budget) 5 Questions? 6 7