Terminal Envelope Upgrade Roof
Replacement Project
August 11, 2026
Commission Meeting
Item No.
8f_supp
Date of Meeting August 11, 2026
Water intrusion and surface
damage has been observed at
the airport terminal central zone
Project will replace the roofing
system to:
o Prevent damage to the building
underlying structural elements
o Preserve the quality of the
environment for people working
in the space below
Project Purpose & Objectives
2
Project scope zone highlighted in yellow
Project Location
3
Schedule Overview
4
Delivery Method: Major Works: Design-Bid-Build
Request single authorization for $6,685,000 for the Executive
Director to take all steps necessary to complete the project
Estimated total project cost is $7,585,000 (design to budget)
Action Requested
5
Questions?
6
7