COMMISSION AGENDA – Action Item No. 10a Page 2 of 6
Meeting Date: August 11, 2026
Template revised June 27, 2019 (Diversity in Contracting).
JUSTIFICATION
The S Concourse facility at SEA opened in 1973 and is owned and operated by the Port. The facility
depends on building systems that are well past their useful service lives, and formerly housed the
federal inspection services, which were relocated to the International Arrivals facility several
years ago. Since the S Concourse was constructed, passenger volumes and aircraft operations
have increased dramatically, security regulations have expanded, passenger level of service
expectations have evolved, and airlines and retailers have changed their marketing strategies.
However, redevelopment of the facility requires updating the space to current building code
minimum requirements. The building systems and materials used in the original construction,
due to their age and manufacture, are difficult to maintain. The facility also contains areas of
encapsulated regulated materials, such as asbestos, which complicates maintenance, renovation,
and development.
Diversity in Contracting
The SCE project includes a 26% WMBE aspirational goal for project management and controls,
and a 12% DBE goal for the design contract. The project team is working with Diversity in
Contracting to identify DBE goals for each separate MACC contract.
DETAILS
This request supports a multi-contract MACC delivery approach which allows the team to
sequence work efficiently, manage risks, and pursue cost saving and schedule acceleration
opportunities as design progression and market conditions evolve. The program currently
anticipates approximately six MACCs to complete construction. This request will fund the
program through what is currently anticipated to be the first 4 MACC contracts and preparation
of the fifth. Funding supports but is not limited to design, project management, construction
management, procurements, preconstruction services and funding for the construction of the
scopes of work currently planned for the first 4 MACC contracts. As design and scheduling
progress, the number of MACC contracts covering this scope of work may vary.
The scope of work included in this authorization includes temporary facilities, early work scope
elements including baggage system modifications, demolition, regulated materials removal, civil
infrastructure, structural, and electrical systems. Also included is procurement of long lead
materials such as vertical transportation, passenger loading bridges, select mechanical and
electrical equipment, and curtainwall system. The scope also includes project components to
support the construction of the S Concourse, such as the Interim S Annex holdroom and other
ancillary support facilities.
The S Concourse Evolution (SCE) project delivers a comprehensive modernization of the 50-year-
old facility, addressing critical seismic, structural, and building systems deficiencies while
improving passenger circulation, revenue generation and operational efficiency. The design