COMMISSION
AGENDA MEMORANDUM
Item No.
8e
ACTION ITEM
Date of Meeting
July 28, 2026
DATE : June 24, 2026
TO: Stephen P. Metruck, Executive Director
FROM: Sarah Ogier, Director, Maritime Environment & Sustainability
Jon Sloan, Sr.Manager, Environmental Programs
Kathleen Hurley, Sr. Program Manager, Maritime Environment & Sustainability
SUBJECT: Duwamish Basin Steward ILA Amendment
Amount of this request:
$26,000
Total estimated project cost:
Up to $150,000
ACTION REQUESTED
Request Commission authorization for the Executive Director to approve a 1-year extension of
the Duwamish Basin Steward Interlocal Agreement through December 31, 2027.
EXECUTIVE SUMMARY
This request is to approve a 1-year extension of the Duwamish Basin Steward ILA through
December 31, 2027. This date extension correctly aligns the agreement with the anticipated five-
year term. The purpose of the agreement is to deliver Basin Stewardship services and provide a
mechanism to promote, develop, and implement environmental stewardship projects within the
Duwamish Service Area.
This Interlocal Agreement (ILA) funds stewardship capacity for the Duwamish Service Area to
focus on land conservation and habitat restoration, community engagement and partner
coordination, as well as improved environmental sustainability of the Duwamish Valley industrial
complex along the river’s shorelines. Additionally, the ILA supports each entity’s development
and implementation of Chinook salmon habitat restoration projects, conservation of open space,
and collaboration with community organizations and private businesses to promote creative
solutions for stormwater management, floodplain restoration, riparian restoration, climate
adaptation, and other environmental activities within the service area.
COMMISSION AGENDA Action Item No. 8e Page 2 of 4
Meeting Date: July 28, 2026
Template revised June 27, 2019 (Diversity in Contracting).
JUSTIFICATION
The Port’s participation in this ILA supports Century Agenda goals around equity and
environment, specifically habitat restoration in areas in which the Port operates. The Duwamish
Basin Steward plays an important role in coordinating habitat restoration and stewardship efforts
for optimal impact throughout the service area. This ILA was added to the 2022 budget per
request by Commissioner Felleman and through the Commission Budget Request process.
Port support for the Duwamish River steward is in alignment with the Duwamish Valley
Community Equity Program which was adopted by the Port Commission in 2019. The Duwamish
Valley Community Equity Program aims to harness the Port’s economic development mission to
promote community partnerships, healthy environments and communities, and economic
prosperity.
Diversity in Contracting
The Port will not conduct any procurement under this ILA.
DETAILS
The ILA created a dedicated position for a Duwamish Basin Steward (hired and managed by King
County) that supports collaboration and advances restoration efforts with communities in the
Duwamish Service Area.
This ILA provides a mechanism for securing technical assistance and funding from federal and
state agencies and other sources to undertake habitat stewardship activities in the Duwamish
Service Area. The service area includes the Duwamish sub-watershed, as defined in the WRIA 9
Plan, as well as two unincorporated urban areas that overlap in part with the Duwamish sub-
watershed, North Highline area (between Seattle and Burien) and the Skyway unincorporated
area, extending to Lake Washington.
The original agreement remains in effect until December 31, 2026 and this request would extend
the duration of the agreement by one year to December 31, 2027. Should the Port decide to exit
the agreement, there are provisions within the ILA to do so, as well as options for extending the
ILA beyond the five-year time period, upon execution by each party, which we are exercising in
this instance.
Scope of Work
Each party to the ILA has one representative on the Duwamish Basin Management Team (DBMT).
The DBMT manages the Duwamish Basin Stewardship program (“Duwamish Program”) for
carrying out the basin stewardship purposes of the ILA and defines the scope of the basin
steward’s work.
COMMISSION AGENDA Action Item No. 8e Page 3 of 4
Meeting Date: July 28, 2026
Template revised June 27, 2019 (Diversity in Contracting).
The DBMT meets at least four times per calendar year, and more frequently if the DBMT
determines it necessary, to review Duwamish Program workplan progress, as well as partnerships
that would benefit the Program, including potential funding. Each year, prior to October 1, the
DBMT shall develop a draft work program and budget for consideration by the DBMT for the
following calendar year.
King County performs day-to-day project management and direction and communicates with
other DBMT participants as needed to conduct Duwamish Program activities. King County will
schedule, facilitate, and provide summaries of all DBMT meetings to each Party during
implementation of the Duwamish Program.
Schedule
If the amendment is approved, this agreement will end December 31, 2027. During 2027, the
team will consider a new ILA for a new term.
Cost Breakdown
Total Project
2027 Duwamish Basin Steward
$0
$150,000
Total
$0
$150,000
FINANCIAL IMPLICATIONS
The projected annual expenditure for the Port’s share in 2022 was $26,000, which represents
12.5% of the Duwamish Basin Steward position cost. The cost of the basin steward is shared by
King County, the City of Tukwila, the City of Seattle, and the Port. The Port’s share is 12% of the
total cost annually ($26,000 in 2022), subject to adjustment for inflation based on the Consumer
Price Index for Urban Wage Earners and Clerical Workers (CPI-W). The initial term of the ILA was
five years and approximately $150,000 total through December 31, 2026. Given delays in
finalizing the ILA, the Basin Steward position did not begin until 2023, and this extension will
support the full timeframe of 5 years for the position and the same original 5-year cost. Port staff
will include an annual budget request to support the position in 2027. The Port’s estimated cost
share (12.5%) in 2027 is $30,000.
COMMISSION AGENDA Action Item No. 8e Page 4 of 4
Meeting Date: July 28, 2026
Template revised June 27, 2019 (Diversity in Contracting).
ADDITIONAL BACKGROUND
The ILA was intended to support 5 years of work in the Lower Duwamish/Green River, beginning
in 2022-2027. However, two issues delayed the start of work: 1) the ILA was not fully executed
until February 2023, due to unanticipated delays in the approval and signature process among
the four entities; and 2) the ILA expiration date of December 2026 was not updated to December
2027 during the signature process, thus effectively shortening the intended 5 year duration of
the agreement to only 4 years. The cost of the basin steward is shared by King County, the City
of Tukwila, the City of Seattle, and the Port. The Port’s share is 12.5% of the total cost annually
($30,000 in 2027), subject to adjustment for inflation based on the Consumer Price Index for
Urban Wage Earners and Clerical Workers (CPI-W).
ATTACHMENTS TO THIS REQUEST
(1) Amendment to interlocal agreement for Duwamish Basin Steward
(2) Initial interlocal agreement for the Duwamish Basin Steward
(3) Presentation
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
May 24, 2022 (item 10b) The Commission authorized the Executive Director to execute an
interlocal agreement with King County, City of Seattle, and City of Tukwila for the
Duwamish Basin Steward position.