COMMISSION AGENDA – Action Item No. 10a Page 4 of 5
Meeting Date: July 14, 2026
Template revised June 27, 2019 (Diversity in Contracting).
FINANCIAL IMPLICATIONS
This request increases the overall Post-IAF Airline Realignment project budget by $3,752,000,
resulting in a revised total estimated project cost of $158,252,000. Of the $3,752,000 increase,
$3,252,000 is for the Concourse B UA Lounge and $500,000 is for remaining Airline Realignment
scope that is directly managed by the Port.
The Concourse B UA Lounge total project cost is now projected at $21,252,000. The $15,500,000
construction TRA with UA is included within the $21,252,000 UA Lounge total.
The current authorization request is $17,352,000. This authorization request includes previously
budgeted but not yet authorized funds, plus the current $3,752,000 budget increase, and
provides the authority needed to execute the UA construction TRA and authorize the revised
total project budget.
Cost Estimate/Authorization Summary
Current request for authorization
Total authorizations, including this request
Annual Budget Status and Source of Funds
This project, CIP C801158 was included in the 2026-2030 capital budget and plan of finance with
a capital budget of $153,575,000 and an expense budget of $925,000 for a total cost of
$154,500,000. This request increases the total project budget by $3,752,000, from $154,500,000
to $158,252,000. The budget increase supports both the Concourse B UA Lounge and remaining
Airline Realignment scope. As reflected in the Cost Estimate/Authorization Summary, the current
budget increase includes $2,711,000 capital and $1,041,000 expense.
The requested budget increase for the Concourse B UA Lounge and the supplemental increase
for Airline Realignment scope is presented together because they are part of the same CIP and
share the same funding source. Funding sources will remain consistent with the broader Post-IAF
Airline Realignment project.