Project Purpose & Objectives
• The Main Terminal Improvement Program – Emergency Power (MTIP) will provide
emergency power to the Main Terminal and Concourses B, C, and D. The emergency
power is required by code and drives the smoke control systems of the Main Terminal
and concourses, ultimately improving the safety of the airport.
• This Sustainability Framework Tier One project is electrical in nature and due to its
emergency use condition, is driven by National Electric Code requirements.
• The project requests to move forward to 30% design at a cost of $7M. At completion
of 30%, the team will be back to ask for the remaining amount.
2