Item No. 11a_supp Date of Meeting April 28, 2026 S Concourse Evolution (SCE) Program Update Background • The SCE Project is a critical infrastructure renewal effort at SEA, addressing the 53-year-old facility's seismic, structural, and code compliance needs while enhancing the passenger experience. SCE project will renew this important regional facility through two main objectives: o Extend the useful life and bring the facility up to current code including structural and seismic upgrades o Re-purpose space left vacant by services relocated to the International Arrivals Facility (IAF) and enhance the passenger experience by increasing amenities, expanding dining and retail (ADR) opportunities, and elevating the level of service. 2 Facilitating Projects • Convert existing parking area at Cargo 3 for GSE Storage • Improve existing Cargo 6 location to allow for Passenger Operations • Convert existing Gate D6 from a bussing gate back to a Passenger Loading Bridge • Construct duct bank from Cargo 7 to Generator Yard and across 188th St to S Main Substation 188th St. Ductbank Cargo 6 SCE - Base Building Cargo 3 GSE Parking Gate D6 Conversion 3 Facilitating Projects - Active Construction Cargo 3 Cargo 6 Gate D6 4 Supporting Project - Interim S Annex Site Map View looking South 5 Southwest Perspective 6 Northeast Perspective North Perspective 7 Concourse & Upper Concourse View looking East 8 Circulation from STS Train level to Concourse 9 Concourse Holdroom 10 Sustainability Status • 60% Sustainable Design Strategies (SDS) review has been completed - Tracking: • 12% reduction in annual energy consumption • 50% reduction in annual operational carbon emissions • 25% reduction in embodied carbon emissions • 23% reduction in annual potable water consumption - Equity inclusions: • Food donation center • Employee break room • Pursuing the United States Green Building Council's (USGBC) Leadership in Energy and Environmental Design (LEED) Silver Certification (minimum) 11 Budget/Schedule Status • Project schedule improved to 7 years and 10 months, with substantial completion 4Q 2034 o Previous 30% schedule was 9 years and 4 months, with completion 1Q 2036 • Program budget established at ~$2.5B o Reduced from 30% estimate range of $2.9 - $3.3B 12 Next Steps Note: Action items subject to change 13 Questions? 14 Thank you! 15