FT C-15 Building Improvements
Commission Construction Funding Request
PN: N10301, CIP: 801096
April 28, 2026
Rod Jackson/ Jessica Carlson
Item No.: 10c_supp
Date of Meeting: April 28, 2026
Overview
• Project Information
• Project Scope
• SEF (Sustainable Evaluation Framework)
• Cone of Certainty
• Schedule
2
Project Information
C15 is the centerpiece of Fishermen’s Terminal and includes:
• A waterfront plaza, Port of Seattle offices, tenant office space, restaurants, and stores. The multi-use building is
operational 7 days a week.
Project details:
• Sponsors: Jennifer Maietta, Director RE Asset Management and Jessica Carlson Senior Real Estate Manager
• Current Estimated Project Cost: $17,267,000
• Current Estimated Construction Cost: $16,467,000
• Previously Requested Authorization: $800,000 for Seed money and Design
TODAY’S REQUEST:
• Request Commission authorization for the Executive Director to approve funding to advertise and execute a
major public works construction contract for the completion of the Fishermen’s Terminal (FT) C-15 Building
Improvements Project. This request is in the amount of $16,467,000 for a total estimated project cost of
$17,267,000.
3
Project Scope
4
• Roof overlay and insulation
• Gutters, rooftop vents
• Solar panels
• Cladding and insulation
• Update storefront doors and thresholds
• Triple pane windows
• Tower structure repairs
• Removable mechanical well roofs
• Art – Mary Coss – Neon Rope
• RGB LED and plaza lighting
• Bike lockers, community board, and
picnic tables
• Biofiltration planters and oyster barrels.
• Compliance with State and City building
energy codes.
Architectural Rendering of C-15 with Solar Panels and New Facade
Sustainable Evaluation Framework
5
• Building Energy
– Rooftop solar
• 10-20% of building energy use
• ROI 10 years
• Lifetime Carbon Reduced: 96 tCO2e
• 170,000 kWh produced annually
– Cladding, insulation, LED lighting, triple pane
windows, exterior sunshades
• 46% building energy use reduction
• ROI: 40 years
• Lifetime Carbon Reduced: 955 tCO2e
Note: Estimates are all rough-order-magnitude based on preliminary pre-design assumptions
Waste
Salvage windows and metal siding (11.5 tons)
Stormwater
Install above-code stormwater treatment on
downspouts
Materials
Procure select red list free materials
Equity
Improve plaza lighting
Keyless bike lockers
Community board
Picnic tables
Update doors and thresholds for accessibility
Cone of Certainty
6
We are here
Preliminary Schedule
Commission Authorization - Construction April 28, 2025
Notice to Proceed
2026 Quarter 4 or
2027 Quarter 1
In-use date 2027 Quarter 4
7
8
Questions?
Questions?