Item No: 8h_supp Meeting date: April 14, 2026 Fishermen's Terminal Redevelopment Request for Additional Funding for Close-out Action Requested Request Commission authorization for the Executive Director to additional funding in the amount of $500,000 for close-out costs for the Fishermen's Terminal Maritime Innovation Center (MInC) (C801084) and Site Improvements (C801211) projects. 2 Close-Out Cost Needs • Significant unforeseen conditions found during construction - Contaminated soil and two underground storage tanks found in the primary ground disturbance area that required contamination remediation that exceeded the approved ERL funding by $210,000 - Unforeseen issues caused four months delay and a Level 1 delay claimed settled early between Port and contractor - Increased anticipated soft costs due to delays from unforeseen conditions depleted remaining contingency of the project. • Additional funds are required to finalize the ERL costs and complete all close-out tasks. • Some of these funds are expected to be offset by liquidated damages. The amount is still in negotiation. 3 Financial Summary Cost Breakdown This Request Total Project Design Includes MInC Public Site Improvements $0 $0 $3,650,000 $1,525,505 $210,000 $810,000 $160,000 $290,000 30,690,495 Environmental Remediation Liability Soil Remediation Abatement Construction MInC & Public Site Impr1 Public Art Total $482,000 $500,000 $37,358,000 4 Construction Schedule Milestones Commission construction authorization Advertise for construction bids Construction contract execution (enabling start of verification period by Contractor) Construction Notice to Proceed issuance Construction Start Substantial construction completion 08/08/2023 08/28/2023 November 2023 May 2024 05/31/2024 03/06/2026 5 Questions 6 7 7 Design Elements • Used the existing building footprint from 1918 • Building completely renovated utilizing existing beams and replacing building skin with clad materials • All-new exterior envelope including new glass exterior windows and doors to enhance transparency and fresh air and light • Seismic upgrades including new steel supports along wood beams • New building systems • Living Building Challenge 8 Building Improvements • Abated regulated materials in existing structure • Partial existing building demolition (timber structural framework preserved) • Utility services removal and replaced • New building perimeter and parking lot paving • Artistic lighting • Polycarbonate west wall, and north facing skylights 9 9 Fishermen's Terminal Site Improvements LANDSCAPE • • • • Landscape Planting Parking Striping Crosswalk Improvements Site Furniture SIGNAGE • • • Interpretative Signage Wayfinding Signage New Monument Sign ELECTRICAL • Site Lighting 10 10 1% For Public Art 11 Living Building Challenge Sustainability Commitment 12 12 13 13