
COMMISSION AGENDA – Action Item No. 8g Page 4 of 5
Meeting Date: April 14, 2026
Template revised June 27, 2019 (Diversity in Contracting).
FINANCIAL IMPLICATIONS
Current request for authorization
Total authorizations, including this request
Remaining amount to be authorized
Annual Budget Status and Source of Funds
$3.9M of the $6.3M total has been allocated to the Port’s ERL for 2026. The remaining $2.4M
was an unplanned expense that has been accrued to 2025. All funding will come from the Port’s
Environmental Legacy Fund or Tax Levy.
ATTACHMENTS TO THIS REQUEST
(1) Presentation Slides
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
June 4, 2024 – The NWSA Managing Members approved use of “design-build” as an
alternative to “design-bid-build: for the Terminal 5 Container Expansion Project, U00712.
August 1, 2023 – The NWSA Managing Members authorized for the Chief Executive Officer or
their delegate to enter into the Third Amendment to the Terminal 5 lease with SSA
Terminals (Seattle Terminals), LLC eliminating the Phase 1 Plus premise and to certain
improvements and the financial responsibility for such improvements and to commence
Phase 2 operation on January 1, 2024, in substantially the same form as presented.
August 2, 2022 – The NWSA Managing Members authorized for the Chief Executive Officer or
their delegate to approve the Third Amendment to the Terminal 5 lease with SSA
Terminals (Seattle Terminals), LLC to commit early to the Phase 2 of the Terminal 5 Lease
eliminating Phase 1 Plus premises and to certain improvements and the financial
responsibility for such improvements and to commence Phase 2 operation on January 1,
2024.
May 2, 2022 – Briefing to NWSA Managing Members informing that NWSA’s Lease
Obligations were in progress per the agreements with the Tenant. Work is ongoing to
coordinate with the tenant to complete the North Reefer Infrastructure project as a
Tenant Reimbursable project to better meet operations and schedule needs.
July 7, 2021 – The NWSA Managing Members authorized construction for the T5 North Reefer
Infrastructure Project.
July 7, 2021 – The NWSA Managing Members authorized an increase to the Program
authorization in the amount of $50 million, for a total amount of $390 million, for the
Terminal 5 Berth Modernization Program, MID Nos C800132, C800726 and C800988.