Agenda Item: 11a_supp Meeting Date: April 14, 2026 Tax Increment Financing: Grand Connection Crossing Port of Seattle Commission Meeting April 14, 2026 Agenda  Grand Connection Overview  Port Participation in TIF  Next Steps April 14, 2026 Tax Increment Financing - Grand Connection Crossing 2 Grand Connection Crossing will promote connectivity and livability April 14, 2026  This bike-ped crossing over I-405, roughly a half-mile in length, will connect downtown Bellevue to the redeveloping Wilburton neighborhood.  People both walking and biking will be able to travel east-west with ease and safety thanks to separated facilities.  It will catalyze Wilburton's transformation into a mixed-use, transit-oriented neighborhood with housing choices for people of all incomes. Tax Increment Financing - Grand Connection Crossing 3 Grand Connection will connect key regional growth centers, drive up tourism  Accessible by light rail from SEA and Seattle, including downtown cruise ship terminals  Investment in active transportation and open spaces projected boost retail and tourism  Based on a 2025 HR&A analysis of similar projects, we expect to see: o Increased leisure visits and an increase in employment in the tourism industry o Shoppers who will spend up to 9-12% more when buying goods in areas with greater open space o Up to 3 times the amount of people staying in enhanced open spaces, such as at cafes or on park benches. April 14, 2026 Tax Increment Financing - Grand Connection Crossing 4 Facilitating both transit-oriented and trail-oriented development  Bellevue's June 2025 upzone will enable transit-oriented development of up to 450' along the north-south spine of Wilburton.  Robust ped and bike connections, including the 42-mile regional Eastrail corridor  Magnet for major employers, including T-Mobile, TikTok, OpenAI, Amazon, Snowflake, and more April 14, 2026 Tax Increment Financing - Grand Connection Crossing 5 Tax Increment Financing (TIF) Overview What opting-in means for Port of Seattle Funding commitments  Total project cost estimated at $200-230 million  Funding committed to date:  $2.5 million: Friends of the Grand Connection  $46.7 million: Bellevue's 2025-3031 Capital Investment Program  TIF is expected to cover 20-30% of debt service April 14, 2026 Tax Increment Financing - Grand Connection Crossing 7  TIF captures property taxes generated from increased assessed value (AV) on the sites that redevelop within the TIF boundary  Only revenues from regular property taxes assessed against the increment value are captured: Assessed Value (AV) TIF Model April 14, 2026 Incremental AV Incremental Real Property Tax captured by City of Bellevue to pay project costs TIF District Total AV now belongs to all Taxing Districts BASE AV AV belongs to all taxing districts overlapping TIF District  To pay public improvement costs  To repay bonds issued for public improvements NEW Post-Project AV Created 25-year TIF (estimated) Tax Increment Financing - Grand Connection Crossing Terminated 8 Proposed Tax Increment Area (TIA)  Delivered to State Treasurer January 14, 2026  Shared with taxing jurisdictions on January 16, 2026  $500M assessed value maximum (0.06% of King County AV)  Analysis models three development scenarios that could result over the life of the TIF because of the Crossing project: • Full, Phased, and MarketResponsive Limited Buildout April 14, 2026 Tax Increment Financing - Grand Connection Crossing 9 Financial Impacts for the Port • Taxing districts give up direct access to some revenue in the near term but benefit from long-term growth in assessed value. • If a taxing district has not reached its statutory levy limit, it is permitted to increase its tax rate slightly to recover the revenue that is allocated to the TIA. • This is provided by state law in an effort to cause "no harm" to taxing districts in TIF areas 25-year TIF (2027-20252) Development Scenario Limited Taxes Allocated to TIF Total Taxes to Port $1,407,000 $1,476,000 Total taxes apportioned from the Port to the city $1.41 million, slightly below the district levy growth of $1.48 million, which includes $66,000 from new construction and $1.41 million from the increment. 10 Next Steps  Request Commission action on TIF by early May  Bellevue City Council will consider taking action in May to establish the Tax Increment Area  Funding decisions for TIF are part of the city budget process later this fall April 14, 2026 October 19: Shared Preliminary Project Analysis with Taxing Districts January 16: Submitted Project Analysis shared with Taxing Districts April 28: Bellevue City Council provides direction on establishing the Tax Increment Area (TIA) May 19: Potential action by Bellevue City Council to establish the Tax Increment Area (TIA) Tax Increment Financing - Grand Connection Crossing 11