Terminal 91 West Cruise Berth Dredge
Updated Project Authorization - ERL
Linda Springmann – Director, Cruise & Elliott Bay Operations
Julie Yun – Capital Project Manager, Waterfront Project Management
Item No.: 8f_supp
Meeting Date: February 24, 2026
Agenda
• Commission Action Requested
• Project Objectives
• Project Scope
• Schedule Risk
• Project Cost
• Project Schedule
• Questions
2
Action Requested
Request Commission authorization for the Executive Director to:
Approve the updated project authorization request to include
the Environmental Remediation Liability (ERL) project in the
amount of $250,000 for a total authorization of $550,000 in ERL
funding and $750,000 in Operating Expense for the Terminal 91
West Cruise Maintenance Dredging project. Total authorization
including this request is $1,300,000 and full project is expected
to total $3,250,000.
3
Project Objectives
• Secure adequate maneuvering room for
both Starboard- and Port-side tie of cruise
vessels to support Commission Order No.
2024-08, committing all Port facilities to be
service-ready for cruise ships to utilize
shore power by 2027 Cruise season.
• Comply with MTCA Agreed Order No.
DE24768 and all MTCA site requirements
for Interim Action Work.
• Minimize construction impacts to the
natural environment and tribal fishing.
4
Project Scope
• Perform maintenance dredge at Main West channel and
Southeast pier face to restore full under keel clearance to
previously dredge depth of -35 ft MLLW.
– Approximately 3,000 CY will be dredged at Main West channel
– Approximately 500 CY will be dredged at Southeast pier face.
– Dredging at the Southeast pier face will follow all dredging, testing,
and disposal requirements per MTCA Agreed Order No. DE24768.
• Minimize impacts to natural habitat and water quality.
• Minimize construction impacts to tribal fishing.
5
Project Scope: Dredge Footprint
6
T91 Pier 91
Main West Channel
Southeast High spots
Project Risks
7
MitigationImpactProbabilityDescriptionRisk
Proactive engagement with
federal/local agencies, tribes, etc.
to ensure timely progress toward
full permit approval.
HighMed
Federal in-water permit review and approval
turnaround time; unforeseen government
shutdown/resource constraints
Permit Delay
Proactive collaboration with
agencies and GC to establish
protocol for safe
screening/disposal of found
DMM’s.
MedLow
DMM discovery during construction will halt work
until notification to resume work is issued.
Presence of
Discarded Military
Munitions (DMM)
Proactive communication and
coordination between internal
Port staff and GC to manage
resource capacity and phasing.
LowLow
Existing MC-Unit Price Dredging contract with single
general contractor (GC) will be shared across
multiple dredge projects.
Contract Risk
Project Cost
8
Total ProjectERLEXPENSEItem
$1,050,000$300,000$750,000Previous Authorizations
$250,000$250,000$0Current request for authorization
$1,300,000$550,000$750,000
Total authorization, including this
request
$1,950,000$0$1,950,000
Remaining amount to be
authorized
$3,250,000$550,000$2,700,000Total project cost estimated
Project Schedule
9
Anticipated DateItem
Q4 2025DORA – Design Authorization
Q1 2026Commission – Updated Design Authorization (ERL)
Q3 2026Design & Permitting Complete
Q4 2026Commission – Construction Authorization
Q4 2026Construction Start
Q1 2027Substantial Completion
April 20272027 Cruise season start
Questions
10