Terminal 91 Berth 6 & 8 Redevelopment
Additional Construction Funding
Linda Springmann, Director of Cruise Business and Elliott Bay Operations
Brian Sweet, Director, Engineering Construction Management
Mark Longridge, Capital Project Manager, Waterfront Project Management
Item No.: 8d_supp
Meeting Date: February 10, 2026
Action Requested
2
Request Commission authorization for the Executive Director to approve
additional funding for completion of the Terminal 91 Berths 6 & 8
Redevelopment project, to resolve all outstanding contractor claims, and
advance the completion of the berth elements to allow for fishing fleet
use in 2026.
Total request for this action will be $3,300,000 for a project total
authorization of $101,300,000.
Project Location
N
3
Project Location
4
Construction currently 85% complete
5
Jan 2026Feb 2025
Sep 2024
Construction changes / site conditions
6
Proposed claims resolution
• Single negotiated claim resolution with the prime contractor
• This would cover all existing and future claims to complete the
work and additionally include any acceleration required to
bring the berths into service in March 2026, approximately 4
months earlier than the remainder of the project
• Additional funding of $3.3M includes the required contract
contingency increase from 10% to 13%, plus additional soft
costs to complete the work due to lengthened schedule and a
revised total substantial completion of July 2026
7
8
Discussion/Questions?
Previous Condition
9
• Creosote timber construction
• Significant underdock and fender deterioration
Pier Replacement
10