
COMMISSION AGENDA – Action Item No. 8d Page 3 of 5
Meeting Date: February 10, 2026
Template revised June 27, 2019 (Diversity in Contracting).
The redevelopment includes demolition of approximately 62,250 square feet of condemned
existing timber apron and replacement of approximately 780 linear feet of seawall (northerly
portion of Berth 6 and entire Berth 8), removal and relocation of existing gangway, floats and
boathouse, removal/replacement of existing small office structures, and reconstruction of a
concrete apron structure at 600 pounds per square foot load capacity along the current
alignment. The project includes the removal of over 2,200 failing creosote piles, installation of
approximately 320 concrete and steel piles, with an overall decrease in overwater coverage. The
project work also includes stormwater improvements, upgraded shore power connections,
renewable energy through new solar panel arrays, and a direct connection for vessel sanitary
sewer.
Scope of Work
This project provides significant waterside and landside improvements, including the following:
Dock demolition and replacement, relocation of boat house and removal of existing small
boat floats. Demolition of the existing pier deck and structure, including removal or cutoff
of approximately 2,200 existing creosote piles. Removal and regrading of the existing
under pier slope and replacement of the upland sheet pile wall.
Placement of approximately 240 prestressed concrete structural piles and approximately
80 steel fender and guide piles, placement of 4 feet of riprap rock and habitat fish mix,
placement of the new concrete precast deck panels, bullrail, utilities, bollards, upgraded
shore power connection points and appurtenances.
Removal of the existing buildings A-310 building (currently leased by American Seafoods),
A-300, A-400, A-301, A-500, A-501 (occupied by Port Operations and police), removal of
existing pavement and installation of deep soil mixing soil amendments, stormwater
treatment system, and surface regrading.
Replacement of the six existing buildings with two new modular buildings for tenant and
Port use, paving and striping, installation of electric vehicle charging infrastructure, and
installation of modernized electrical substation to service the buildings and vessels at the
pier.
Schedule
Currently the construction is approximately 85% complete and anticipated to reach Substantial
Completion in July of 2026 based on the latest contractor schedule. Acceptance of the negotiated
agreement with Pacific Pile and Marine would allow both berths to begin operations
approximately 4 months earlier in March 2026.