We completed an audit of the Terminal 91 Berths 6 & 8 Redevelopment Project for the period of February
2024, through June 2025. The audit was conducted to assess the effectiveness of the procurement and
construction management processes. It also provided an independent evaluation of the Port of Seattle’s
(Port) management practices, specifically in processing pay applications and monitoring unit price items
and tariff charges.
KPFF, the independent engineer, estimated the cost of this project to be $49,615,105. The two lowest
proposers had bids of $72,636,235 and $72,695,500 respectively, accordingly, this .08% difference in
bids and the significant increase from the engineer’s estimate raised concerns. As part of our review,
we assessed bid submissions for irregularities. Our analysis did not identify common red flags such as
rotation of winning bidders; use of losing bidders as subcontractors…etc. However, we observed that
two bid items had identical amounts from the two lowest bidders, and these had notable variances from
the engineer’s estimates. This could likely be the result of both firms getting estimates from the same
local sub-contractor. While these patterns do not constitute evidence of irregularities, they warrant
continued awareness and monitoring.
In February 2024, the Port entered into an agreement with Pacific Pile and Marine LP using a Design-
Bid-Build approach with a lump sum delivery method. This was supplemented with certain scope-of-
work line items reimbursed on a cost-of-work basis. The original contract value was approximately $72.6
million. Following two change orders, the substantial completion date has been extended from
December 28, 2025, to January 11, 2026.
We identified control gaps in the pay application review process. Several pay applications were
approved and paid without supporting documentation to substantiate the amounts billed, resulting in an
overpayment to the contractor. This observation underscores the importance of adhering to the Port’s
Standard Operating Procedures (SOP). Reinforcing internal controls will help reduce the risk of
overpayment and assure compliance with SOPs.
This opportunity is listed below and discussed in more detail beginning on page six of this report.
1. (Medium) Engineering Construction Management (EN-CM) did not obtain sufficient documentation
from the contractor to adequately review pay applications for accuracy. This resulted in a net
overpayment of $147,377.
Glenn Fernandes, CPA
Director, Internal Audit
Responsible Management Team
Stephanie Jones Stebbins, Managing Director Maritime
Tin Nguyen, Director Waterfront Project Management
Brian Sweet, Director Engineering Construction Management
Janice Zahn, Chief Engineer