COMMISSION AGENDA – Action Item No. 8e Page 3 of 4
Meeting Date: November 18, 2025
Template revised June 27, 2019 (Diversity in Contracting).
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 – Maintain full project scope and complete all work as planned.
Cost Implications: $ 3,937,000
Pros:
(1) All elevators of the Parking Garage will be completed to enhance passenger experience
(2) Allows for the replacement of existing elevators that are at the end-of-life condition
(3) Maintain the Port’s overall design theme
Cons:
(1) Additional capital expenditure
This is the recommended alternative.
Alternative 2 – Stop construction activities prior to completion. Do not complete full project
scope.
Cost Implications: $23,090,000
Pros:
(1) None
Cons:
(1) The project cannot be completed as planned. High risk of elevator failure; high risk of
negative impact to airport operations and passenger service.
This is not the recommended alternative.
FINANCIAL IMPLICATIONS
ost Estimate/Authorization Summary Capital Expense Total
COST ESTIMATE
Original estimate $ 23,276,000 $0 $ 23,276,000
Previous changes – net $ (180,000) $ 180,000 0
ART Transfer $ (186,000) 0 $ (186,000)
Current Change $ 3,937,000 $ 3,937,000
Revised estimate $ 26,847,000 $ 180,000 $ 27,027,000
AUTHORIZATION
Previous authorizations $ 23,096,000 $ 180,000 $ 23,276,000
ART Transfer $ (186,000) 0 $ (186,000)
Current request for authorization $ 3,937,000 $ 3,937,000
Total authorizations, including this request $ 26,847,000 $ 180,000 $ 27,027,000
Remaining amount to be authorized $0 $0 $0