COMMISSION AGENDA – Action Item No. __8c__ Page 2 of 5
Meeting Date: November 11, 2025
Template revised June 27, 2019 (Diversity in Contracting).
Diversity in Contracting
The design service is using a project specific designer with a diversity in contracting commitment
of 19%. The consultant is on track to exceed that commitment with a project utilization of 24%.
The WMBE aspirational goal analysis for construction is 5% due to a large percentage of the
construction cost being the equipment installed for the project.
DETAILS
Scope of Work
Work will include the demolition of existing obsolete equipment, installation and commissioning
of the new equipment, and removal of the old systems. These components include, but are not
limited to, the following:
(1) Conduct abatement of regulated materials (existing tanks and associated piping are
known to be wrapped in asbestos insulation).
(2) Remove and dispose of the boiler room air handling unit to create space for the new DA
and condensate tanks and equipment.
(3) Remove and dispose of the obsolete air compressors and the associated equipment to
create space for the new DA and condensate tanks and equipment.
(4) Install the new the DA and condensate tanks, piping, and equipment necessary to
replace the existing system.
(5) Install new feedwater and condensate pumps (6 pumps total).
(6) Install new Variable Frequency Drives (VFD's) and controls to improve efficiency.
(7) Perform foundation upgrades as required, per new building codes, to support new
tanks, equipment, and platform.
(8) Construct a platform around the new tanks and a new catwalk platform around the
boilers’ steam header for ease of maintenance and safety.
(9) After the installation and commissioning of the new equipment, remove the obsolete
DA and condensate tanks, pumps, piping, the structural platform the tanks are mounted
on, and all other out-of-use equipment.
Schedule
Activity