
COMMISSION AGENDA – Action Item No. 8j Page 2 of 5
Meeting Date: October 14, 2025
Template revised June 27, 2019 (Diversity in Contracting).
Including a project specific consultant design contract anticipated to be in the range of $15 – $22
million, the total remedial design effort’s cost is preliminarily estimated to be approximately $30
million. Funding for this work was included in the 2025-2029 Environmental Remediation Liability
(ERL) Program. Port Commission approved signing the EPA ASAOC and EWG MOA on September
9, 2025.
BACKGROUND
The Harbor Island Superfund Site is one of the first Superfund sites in the country, listed on EPA’s
National Priorities List in 1983. Harbor Island is a human-built, industrial island in Elliott Bay. Built
in the early 1900s, the 420-acre island supports businesses that conduct commercial and
industrial activities, including a former lead battery recycler, ocean and rail transport operations
and petroleum fuel farm storage and operation. Prior operations at the site resulted in
contaminated groundwater, sediment and soil with lead and other contaminants. The EPA
divided the Harbor Island site into six smaller areas, known as “Operable Units” (OUs) to better
address site cleanup. Cleanups have been completed at five of the OUs, and the remaining OU
for cleanup is the East Waterway. The East Waterway cleanup area stretches one mile along the
east side of Harbor Island and covers 157 acres. It is downstream and north of the Lower
Duwamish Waterway Superfund Site.
The East Waterway requires cleanup due to unacceptable risks to human health and to the
environment. Sediments at the bottom of the waterway contain contaminants that include
polychlorinated biphenyls (PCBs), arsenic, dioxins/furans and carcinogenic polycyclic aromatic
hydrocarbons (cPAHs) that pose risk to human health. There are 29 contaminants, including PCBs
and mercury, which pose risks for benthic invertebrates that are the base of the food chain. PCBs
also pose risk to fish within the waterway. The EPA released its Interim Record of Decision (IROD)
for cleanup of the East Waterway in 2024. The next step to implement the Interim ROD is
Remedial Design (RD).
The EPA ASAOC, requiring the EWG to develop the remedial design for the cleanup; and a new
cost-sharing MOA between the EWG partners, was approved by prior Commission action on
September 9, 2025. Under the MOA, the three EWG parties will share responsibility to implement
the required work. The Port will procure an environmental consulting firm to perform the work,
with costs reimbursed by the City and County on a preliminary basis of 1/3 each. The Port will
hold the contract with the consultant(s) and all invoices will be handled by the Port with
appropriate portions reimbursed by the City and County.
Total cleanup cost estimates were developed for each cleanup alternative as part of the East
Waterway Feasibility Study completed in 2019. In 2023, the EWG updated the cleanup cost based
on the EPA’s preferred alternative as selected in the ROD and updated market pricing for a total
of $419,000,000. Including construction cost escalation and the latest construction market costs,
the current total project cost has been preliminarily estimated at $600,000,000. Of that total,
$30,000,000 is estimated for the requirements of the current EPA ASAOC (remedial design,
baseline monitoring, project management and EPA oversight effort).