Template revised January 10, 2019.
COMMISSION
AGENDA MEMORANDUM
Item No. 8i
ACTION ITEM Date of Meeting September 9, 2025
DATE : September 3, 2025
TO: Stephen P. Metruck, Executive Director
FROM: Jessica Carlson, Sr. Real Estate Manager, Sponsor
Terrence Moody, Capital Project Manager
Jennifer Maietta, Dir. Real Estate Asset Management, Sponsor
SUBJECT: Fishermen’s Terminal C14 Downie Building Demolition and Entrance & Exit Paving
(CIP # 801890) - Design and Construction Authorization Request
Amount of this request: $1,250,000
Total estimated project cost:
$4,400,000
ACTION REQUESTED
Request Commission authorization for the Executive Director to approve funding to (1) Design,
obtain permits, advertise and execute a small works construction contract for PCS to demolish
the Fishermen’s Terminal C14 Downie Building in the amount of $600,000, and (2) Complete
design and permitting of the Entry and Exit Paving project in the amount of $650,000 for a total
request of $1,250,000 for a total authorized amount of $1,550,000. Total estimated project cost
is $4,400,000.
EXECUTIVE SUMMARY
The project will be conducted in two (2) packages. Package #1: Demolish the existing Fishermen’s
Downie Building (Building C-14) which is in the process of being vacated and is unleasable due to
the poor condition of the structure. The demolition will include the abatement of regulated
materials, small amounts of material salvage such as windows, HVAC Systems and doors,
demolition of the structure down to the existing slab, and capping of the utilities. Package #2:
Repave the main entrance and exit lanes of Fishermen’s Terminal and create a parking lot in the
footprint of the demolished C14 Downie building. The existing stormwater catch basin system
and associated piping will be replaced to meet Environmental Stormwater requirements along
with a new biofiltration system. The project will also install upgraded area lighting, three (3) EV
charging stations, a bike lane, bike box, landscaping with pollinator habitat, and wayfinding
signage.
COMMISSION AGENDA – Action Item No. 8i Page 2 of 5
Meeting Date: September 9, 2025
Template revised June 27, 2019 (Diversity in Contracting).
This project is Tier 2 under the Sustainable Evaluation Framework. Analyses are complete and
results included within the scope. The project is currently in the pre-design/phase, with
construction documents at the 30% stage of completion.
The Fishermen’s Terminal facility has been home to the North American Fishing Fleet, provides
vessel moorage, supports many small businesses in multiple buildings including the new
Maritime Innovation Center currently under construction.
JUSTIFICATION
The Fishermen’s Terminal entrance is visitors' first visual experience when entering the facility.
The current condition of the entrance/exit roadway is uneven, marked by potholes, and is
showing clear signs of wear and fatigue. The roadway median is also in a state of disrepair and
needs to be replaced. These elements greatly detract from the visual appeal when entering the
facility. Additionally, the existing stormwater catch-basins, and associated piping must be
replaced to meet Environmental Stormwater requirements. Upgraded lighting, landscaping and
signage will improve the overall aesthetic and operational safety at the entrance/exit of
Fishermen’s Terminal.
The C14 Building was built in 1979 and is now fully depreciated. Major structural upgrades are
required to maintain safe occupancy, but the Port cannot make a business case for rehabilitation.
Without upgrades the building will continue to deteriorate, creating safety and security concerns.
Only one tenant remains in the building, but they will vacate their space in September 2025. As
a result, the building will be demolished.
Diversity in Contracting
Project staff along with the Diversity in Contracting Department have established a Woman and
Minority Business Enterprise (WMBE) aspirational goal of 20% for the construction portion of the
project.
DETAILS
The project team will:
Facilitate small business opportunities by adhering to the WMBE aspirational goals
established for the project.
Mitigate construction-driven business risk impacts by implementing project risk
management and phasing plans.
Complete the project safely, on schedule, and on budget.
Scope of Work
Package #1 Demolition:
Design and obtain permits to demolish C-14 Downie Building down to the slab during
phase 1 utilizing Port Construction Services and the use of Port of Seattle crews and small
COMMISSION AGENDA – Action Item No. 8i Page 3 of 5
Meeting Date: September 9, 2025
Template revised June 27, 2019 (Diversity in Contracting).
works on-call contracts to perform the demolition. Permits include SDCI demolition
permit, stormwater, and grading reviews.
Complete salvage assessment and salvage identified items, including windows, HVAC
systems and doors; complete and submit waste diversion report to SDCI
Cap Building C14 utilities: Natural gas, Water and Sewer
Retain Electrical power for Package #2 build-out.
Package #2 Paving & Drainage:
Regrade and repave the main FT entrance/exit
Remove and replace median & landscaping
Install a new biofiltration swale and landscaping with pollinators
Install stormwater catch basins, piping
Restripe intersection and crosswalks as required
Demolish Building C14 concrete floor slab
Regrade/repave C14 parking lot
Install LED Lighting in new parking lot
Install EV duplex chargers as required by code (3ea)
Install protected bike lanes, bicycle box, and improve connection to W 22nd.
Install improved bicycle and pedestrian lighting within Downie area
Install multimodal wayfinding
Complete ADA compliance as needed
Schedule
Activity
Commission design authorization September 9
th
2025
Design start Demolition & Paving Quarter 3 2025
Construction Demolition for C14 Quarter 2 2026
Commission construction authorization for
Paving & Drainage
Quarter 4 2026
Construction start Paving & Drainage Quarter 2 2027
In-use date Quarter 1 2028
Cost Breakdown This Request
Total Project
Design and Demolition of Bldg. C14 $600,000
$750,000
Design Paving and Drainage $650,000
$800,000
Construction Paving and Drainage $0
$2,850,000
Total $1,250,000
$4,400,000
COMMISSION AGENDA – Action Item No. 8i Page 4 of 5
Meeting Date: September 9, 2025
Template revised June 27, 2019 (Diversity in Contracting).
ALTERNATIVES AND IMPLICATIONS CONSIDERED
Alternative 1 Do nothing, Maintain Status Quo. With this alternative, the C14 Building will
exceed the limit of its service life, the condition of the Entry and Exit Paving will adversely affect
the use of the Facility assets. Maintain the current state and delay upgrades, with continued
maintenance cost of $153K annually (averaged over 12 months).
Cost Implications: $153K/year for maintenance
Pros:
(1) Allows port to reallocate capital investment dollars.
Cons:
(1) Does not advance efforts to achieve Century Agenda goals
(2) Inconsistent with Port standard of care for assets and facilities
(3) Further deterioration of the entry and exit paving with water infiltration disrupting
facility activities and causing damage requiring expensive repairs.
(4) Increased probable construction costs in the future
(5) Safety could be compromised for visitors, tenants and employees.
(6) Maintenance costs will continue to increase
This is not the recommended alternative.
Alternative 2 – Complete demolition of the C-14 Building and improvements of the Fishermen’s
Terminal Entry and Exit.
Cost Implications: $4.4M
Pros:
(1) Advances Century Agenda goal to “Be the greenest and most energy-efficient port in
North America”.
(2) Upgrade and replace components of existing site infrastructure with features that have
a 20-30-year life or more.
(3) Provides protection of Port assets.
(4) Helps to assure a positive visitor experience and demonstrates the Port’s commitment
to maintaining its public facing asset.
(5) The alternative will incorporate Sustainable Design elements approved by the Port
Sustainability, Environment and Climate Committee (SEAC).
Cons:
(1) This alternative uses $4.4M of capital funds that might otherwise be made available for
other uses on other projects.
(2) Short-term construction impacts
This is the recommended alternative.
COMMISSION AGENDA – Action Item No. 8i Page 5 of 5
Meeting Date: September 9, 2025
Template revised June 27, 2019 (Diversity in Contracting).
FINANCIAL IMPLICATIONS
Cost Estimate
/Authorization Summary Capital
Expense
Total
COST ESTIMATE
Original estimate $4,400,000
$0
$4,400,000
AUTHORIZATION
Previous authorizations $300,000
$0
$300,000
Current request for authorization $1,250,000
$0
$1,250,000
Total authorizations, including this request $1,550,000
$0
$1,550,000
Remaining amount to be authorized $2,850,000
$0
$2,850,000
Annual Budget Status and Source of Funds
This project, FT Entrance and Exit Paving (C801890) is included in the draft 2026 capital plan with
a total project cost of $4,400,000. The project was included in the approved 2025 capital plan
with a budget of $2,700,000 and demolition budgeted as a non-operational expense.
This project is funded by the Tax Levy.
Financial Analysis and Summary
Project cost for analysis $4,400,000
Business Unit (BU) Portfolio Management
Effect on business performance
(NOI after depreciation)
Annual depreciation will increase by approximately
$127K based on an estimated 30-year service life,
thereby reducing the NOI by the same amount.
IRR/NPV (if relevant) N/A
CPE Impact N/A
Future Revenues and Expenses (Total cost of ownership)
This replacement project will improve public safety, provide protection of Port assets and extend
the useful life of the Entry and Exit pavement and landscaping. Maintaining existing assets will
preserve the economic vitality of our operations and serve the Port, tenants and their customers
well.
ATTACHMENTS TO THIS REQUEST
(1) Presentation
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS
None