Item No. Date of Meeting S 160th Street Lot TNC Improvements Additional Project Authorization 8j_supp August 12, 2025 Requested Action Request Commission authorization for the Executive Director to take all steps necessary to complete the South 160th Street TNC Lot Improvement Project at Seattle-Tacoma International Airport (SEA). This request is an increase in the amount of $1,100,000 for a total authorization of $8,400,000. 2 Project Purpose Purpose: To minimize operational maintenance costs and encourage sustainable ground transportation services with installation of permanent lighting system and EV chargers. Scope: • Replacement of existing diesel-powered temporary light plants with permanent lighting systems • Installation of ten EV chargers with associated electrical infrastructure upgrades • Installation of four permanent restrooms for TNC operators • Installation of security cameras for operational awareness • Landscaping and irrigation improvements per Port standards 3 Project Location S 146th St 24th Ave S Rental Car Facility N S 160th St S 160th St GT Holding Lot 4 Project Progress Photos TNC Restrooms Electrical Infrastructure 5 SEA's Ground Transportation Framework Guiding Principles • Reduce environmental impact • Reduce roadway congestion • Support and improve customer choice and experience • Social equity • Generate revenue for sustainable airport Goals • 50% scope 3 GHG reduction • 30% private vehicle pick-up/drop-off • 15 minutes tower to curb • Social Equity Strategies and Tactics SAMP e.g. roadway relocation, NE GT Capital Projects e.g. Widen Arrivals Approach GTAP Operational Facility Behavior Change e.g. Modeling, SEA Employee Transportation Strategy (SEA MOVES) e.g. TNC rematch, garage utilization 6 • Financial sustainability Contracts Taxi, TNC, other GT e.g. e-KPIs, GT electrification incentive 6 Project Schedule Completed Work: • Installation of permanent restrooms (Q3 2024) • Installation of permanent lighting (Q4 2024) • Completion of landscape improvements (Q4 2024) • Completion of electrical infrastructure upgrades (Q3 2025) Remaining Work: • Procure EV chargers Q3 2025 • Complete site improvements Q4 2025 • Install and activate EV chargers Q4 2025 7 Project Budget Previous Budget: $7,300,000 Department of Commerce Grant Revised Budget: $8,400,000 • Reimbursement of up to $1,229,322 Budget increase due to: • Port purchase and installation of ten EV fast charging points • Work previously assumed to be completed by third party partner Transformer Electrical Equipment EV Chargers 8 Questions? 9