Item No.: 8h_supp Meeting Date: July 8, 2025 Pier 91/ Pier 66 Cruise Shore Power Extension Project Validation Period for Progressive Design Build Contract - Additional Funding Action Requested Request Commission authorization for the Executive Director to approve additional funding to award and execute the Validation Period of the major public works Progressive Design Build contract for T91/P66 Cruise Shore Power Extension (C801983) project. Total request for this action is $1,100,000 for a total project authorization of $10,450,000. 2 Project Purpose • • • In July 2024, Commission Order No. 2024-08 was passed mandating that all homeport cruise ships connect to shore power by 2027. To meet the mandate, the existing shore power systems need to be extended at Pier 91 and Pier 66. - Currently, the shore power cables cannot reach from the berth connection point to plug-in locations on all shore power capable ships. This project will provide maximum flexibility in how ships with different shore power configurations berth at the pier so they can connect to shore power. 3 Details and Recommendation • A single proposal was received from Skanska USA Building Inc. in response to the project Request for Proposals. • $1,277,000 proposed for Validation Period - 30% over an anticipated $900,000 for the Validation Period. - Validation Fee exceeds remaining authorized budget for procurement, validation and preliminary design. • The additional funds requested in the amount of $1,100,000 cover the difference of the proposal amount that exceeds the remaining authorized budget and to ensure funds are available for required soft costs for early PDB development, project contingency, and taxes. Recommendation: • Accept the proposal received for Validation Period in the amount of $1,277,712 (plus WSST) - Proposal is comprehensive and PDB team is qualified and experienced - Rejecting the proposal will significantly delay the project and implementation will not occur to meet deadline to plugin all homeport cruise ships by 2027 per Commission Order No. 2024-08. 4 Next Steps • • • Progressive Design Build contract execution July 2025 - Validation Period Q3-Q4 2025 Commission Authorization for Design/early work Q4 2025 - Target scope/schedule/cost with PDB Commission Authorization Final design/Construction Q2 2026 - Final GMP, scope, schedule 5 Project Schedule Phases Anticipated Dates Watts Marine Sole-Source Purchasing Contract Authorization Q2 2025 PDB Team Selected / Validation Period of Contract Executed Q3 2025 Validation Period Q3 2025 Early Design Development Authorization (target GMP, schedule, scope) Q4 2025 Final Design & Construction Authorization (final GMP, schedule, scope) Q2 2026 Construction Q3 2026 In-Use 2027 6 Questions? 7 Appendix 8 Project Areas - Pier 91/Pier 66 New shore power connections Area Existing Shore power system New shore power connections Area Pier 91 Pier 66 Pier 66 NewBollard shoreUpgrade power connections Potential Mooring Existing shore power system Pier 91 9 Project Scope • Design and construct all necessary infrastructure upgrades to (2) Pier 91 cruise berths and Pier 66 cruise berth to meet project goals, including : - Conduct a berthing and mooring study for all known current and future ships to determine optimal connection locations, distribution pathways, and required mooring bollard upgrades. - Extend the existing shore-power system to allow all known current and future ships of different configurations to connect to shore-power - Ensure compatibility of the extended cruise shore power system with existing equipment and facilities, including the mobile cable positioning devices (CPD). - Procure all permits - Replacement of existing shore power equipment that has reached end of service life at Pier 91. - New mooring bollards at Pier 91 - Potential limited deck panel replacements at Pier 91 10 Project Funding Cost Estimate/Authorization Summary Capital Expense Total COST ESTIMATE Original estimate $4,000,0000 $0 $4,000,0000 Previous changes - Net* $29,000,000 $0 $29,000,000 Revised estimate $33,000,000 $0 $33,000,000 Previous authorizations • Terminal 91 • Pier 66 • Watts Marine Sole Source Contract $9,350,000 $850,000 $500,000 $8,000,000 $0 $9,350,000 $850,000 $500,000 $8,000,000 Current request for authorization • Terminal 91 • Pier 66 $1,100,0000 $770,000 $330,000 $0 $1,100,0000 $770,000 $330,000 Total authorizations, including this request • Pier 91 • Pier 66 • Watts Marine Sole Source Contract Remaining amount to be authorized $10,450,000 0 $1,620,000 $830,000 $8,000,000 AUTHORIZATION $22,550,000 $0 * The original estimate for this project assumed a single new shore power connection point on the west berth of Pier 91. In July 2024, Commission Order No. 2024-008 was passed requiring all homeport cruise ships to connect to shore power by 2027. To meet the mandate of this order, scope for this project was expanded to include multiple additional connection points on both the east and west berths of Pier 91, as well as adding a third connection point to the existing shore power system at Pier 66. $10,450,000 $1,620,000 $830,000 $8,000,000 $22,550,000 11 Cone of Certainty We are here 12 RISKS DESCRIPTION Constrained Schedule Delivery required by 2027. Minimal work windows due to cruise season, commercial fishing season, tribal agreements, and fish window if in-water work is needed have high potential to delay in-service date past cruise season start in 2027. Two contracts to manage Two contracts to manage: Progressive Design Build (PDB) and Watts Marine sole-source. Scope was separated into (2) contracts to get equipment design and procurement started early to minimize long lead materials issues and due to proprietary shore power technology. Potential for conflicts between contracts causing delays Supply chain uncertainty Supply chain logistics could delay project delivery. Tariffs could impact ability to procure long-lead electrical equipment by 2027, and create uncertainty in pricing. Ownership of the existing cruise shore power system at T91 Ownership is still held by Carnival Cruise. Logistics of ownership transfer could drive up project costs. Coordination with other projects at Terminal 91 Permitting PROBABILITY IMPACT MITIGATION High High Utilize Progressive Design Build project delivery to accelerate timeline. Pre-purchase of long-lead items. Med Clearly defined scope delineation between PDB and Watts in procurement documents. Requirement of NDAs for Watts information to be signed for any interested contractors. Port will facilitate design integration for Watts shore power equipment. High High Adding cost contingencies to account for tariff price impacts. Early execution of Watts contract to begin procurement of long-lead shore power equipment in advance. Med Low Project Risks There are many other projects scheduled on Pier 91 with similar timelines to the cruise shore power project: gangways, water line replacement, dock rehabilitation, west berth dredging. Permitting assumptions are aggressive and assume no inwater work. This could change depending on how the contractor must construct the project. In-water work, or any other permitting delays will delay the project. High Cruise Operations is in negotiation to transfer ownership to the Port. High Med Identification of all on-going and upcoming construction work at Terminal 91. Requirement of logistics plan by PDB to account for constraints of other projects. High High Progressive Design Build project delivery will allow for early collaboration on design and permitting to the extent feasible. 13