
COMMISSION AGENDA – Action Item No. 8f Page 2 of 3
Meeting Date: June 24, 2025
Template revised September 22, 2016; format updates October 19, 2016.
cruise ships by 2027. Acceptance of this proposal would meet the project goal of 6% WMBE
participation.
There were thirteen (13) prime plan holders for the project with only one firm submitting a
Statement of Qualifications and Proposal. The project team determined the following concerns
may have discouraged proposers: very aggressive timeline to achieve in service date, site
congestion during cruise operations and commercial fishing operations seasons, constraints due
to other construction projects, and permitting complexities.
As a PDB project, a robust validation period and preliminary design work are required to
determine the full scope of the project in partnership with the Port of Seattle project team. At
the end of Validation, the Port and the design-builder will negotiate to establish target scope,
schedule, and budget for the project. Following Validation and with Commission authorization of
additional funding, the project will proceed to the next period of the contract to further advance
the design and develop a Guaranteed Maximum Price (GMP).
In July 2024, the Port passed Commission Order No. 2024-08 mandating all homeport cruise ships
to connect to shore power by 2027, three years earlier than the 2030 goal set in the Port’s
adopted Maritime Climate and Air Action Plan. The existing shore power systems at Pier 91 and
Pier 66 need to be extended at both locations to maximize flexibility to enable shore power
connections for all homeport cruise ships by the end of 2027. The target in-service date for
completion is Q1/2027 and closeout scheduled for Q3/2027.
Cost Estimate/Authorization Summary
Capital
Expense
Total
COST ESTIMATE
Original estimate $4,000,000
$0
$4,000,000
Previous changes – net $29,000,000
0
$29,000,000
Revised estimate $33,000,000
0
$33,000,000
AUTHORIZATION
Previous authorizations
Pier 91
Pier 66
Watts Marine Sole Source Contract
9,350,000
$850,000*
$500,000*
$8,000,000
0
9,350,000
$850,000*
$500,000*
$8,000,000
Current request for authorization
Pier 91
Pier 66
Watts Marine Sole Source Contract
$1,100,000
$770,000
$330,000
$0
0
0
0
$1,100,000
$770,000
$330,000
$0
Total authorizations, including this request
Pier 91
Pier 66
Watts Marine Sole Source Contract
$10,450,000
$1,620,000
$830,000
$8,000,000
0
$10,450,000
$1,620,000
$830,000
$8,000,000
Remaining amount to be authorized $22,550,000 $0
$22,550,000