and provide improved operational readiness of the Biffy Facility. The new facility will comply
with current codes, standards, FDA guidelines, and ensure permit compliance, while improving
reliability and operations of this critical facility.
JUSTIFICATION
The Biffy Facility is the only location at SEA that services airplane lavatory waste vehicles. During
the notebook and preliminary design phase of this project, a comprehensive study took place to
evaluate the scope of work, survey the existing facility deficiencies, coordinate with stakeholders,
system experts, and designers to prepare scoping narrative and preliminary design drawings.
There have been releases of sewage onto surface streets due to facility operational failures.
Following a release in October 2024, several other improvements (wet well mixing system,
alarming, level sensors, VFD pumps, etc.) were identified to be added to this project to bring
resiliency to the facility operations and avoid such incidents in the future that could lead to
citations and fines by external authorities.
The original Status 2 document was preliminary in nature and the project scope was only based
on making regulatory improvements to bring the facility up to code and providing redundancy.
Increase in the project scope of work and cost escalation have resulted in an increase to the
budget estimate of $1.6M, bringing the project from the original Status 2 estimate of $4.7M to
$6.3M. Airport leadership approved the additional scope of work and budget in Q2, 2025.
The project will replace the current infrastructure and provide 10+ years of useful life for the
associated equipment. Failure of the vacuum tank or pump system will result in loss of operation
servicing the airplane waste truck and require mobile units on-site during repair. The project will
provide sanitizable, clean-in-place enclosure that meets FDA and NFPA 820 guidelines along with
ventilation, freeze protection, lighting, space heating, redundant pump system with Variable
Frequency Drives (VFD), permanent wet well mixing system, and other electrical improvements.
Diversity in Contracting
The design services will be completed using an existing IDIQ contract (FSI Engineers – P00320721)
that was established in 2022 which has a 16% WMBE participation utilization requirement.
WMBE construction aspiration goal will be established after the completion of the design phase.
DETAILS
The tables below provide a breakdown of the requested increase in budget.
Description Original Budget
(Status 2)
New Budget Total Change
Design $ 1,100,000 $1,500,000 $400,000
Construction $ 3,600,000 $4,800,000 $1,200,000
Total Estimated Cost $4,700,000 $6,300,000 $1,600,000