COMMISSION AGENDA MEMORANDUM ACTION ITEM Item No. Date of Meeting DATE: June 26, 2025 TO: Stephen P. Metruck, Executive Director FROM: Eileen Francisco, Director, Aviation Project Management Keri Stephens, Director, Aviation Facilities and Capital Programs 10a July 8, 2025 SUBJECT: Concourse HVAC Infrastructure Renewal Replacement Project (CHIRRP) - CIP# C801265 GC/CM and Pre-Construction Services Amount of this request: $11,000,000 Total estimated project cost: $255,000,000 $450,000,000 ACTION REQUESTED Request Commission authorization for the Executive Director to (1) advertise and execute a General Contractor, Construction Manager (GC/CM) construction contract and authorize preconstruction services for CIP# C801265. The amount requested under this authorization is $11,000,000 for a total project authorization of $18,250,000. EXECUTIVE SUMMARY The primary focus of the Concourse heating, ventilation, and air conditioning (HVAC) Infrastructure Renewal Replacement Program (CHIRRP) is the replacement of the existing HVAC systems and the addition of smoke control systems within concourses B, C and D. In addition, the project includes ceiling and lighting renewal as well as structural work to support the new penthouses. This project is necessary to maintain continued airport operations and correct code deficiencies that have been impacting planning efforts for the Airport Dining and Retail (ADR), Restroom Renovations, and Concourse Modernization programs. The total estimated project cost is currently $255,000,000 - $450,000,000. The project will return to Commission for full design authorization after 30% design is complete. Project costs and scope will be further developed and refined with the current 30% design effort. The general contractor preconstruction services authorization being requested at this time will be critical in determining the final budget and schedule. JUSTIFICATION The Port recently completed preliminary conceptual design of CHIRRP, some elements of the design scope present risks to overall cost and schedule (gate closures, supplemental AHUs, Template revised January 10, 2019. COMMISSION AGENDA - Action Item No. 10a Meeting Date: July 8, 2025 Page 2 of 6 working on the roof, cranes, etc.). The requested authorization will provide for GC/CM preconstruction services, enabling improved project cost, schedule, and phasing resolution. The plan is to utilize the GC/CM early in the design phase to further evaluate constructability concerns, as well as provide input and feedback on cost saving measures, cost estimates, and schedule. This project has potential to be very disruptive to airport operations and will require complex execution and phasing. The GC/CM early involvement in design development and decisions will help to ensure construction impacts to Airport Operations will be minimized. The 30% design is scheduled to be complete Q2, 2026. This authorization is necessary to ensure adequate participation by the GC/CM in the 30% design development. The Port's goal for the project is to renew and replace end-of-life mechanical equipment and systems while providing adequate future capacity for Port programs. This includes integration of the Port's Sustainable Project Framework to ensure that sustainability and sustainable design alternatives and options are evaluated early in the planning and design process so the project can leverage sustainability options to the greatest extent possible, reducing maintenance requirements, and prolonging the life of the facility. The project will comply with current International Building Code (IBC) and fire code for existing structures and will enhance passenger comfort. The project will also address regulatory requirements such as compliance with Washington Clean Buildings Standards, work to reduce SEA's footprint and lowering costs, as well as compatibility with decarbonization efforts in the Central Plant. Diversity in Contracting The project team in coordination with Diversity in Contracting team has set a 17% women-and minority-owned business enterprise (WMBE) aspirational goal for the design contract for this project. DETAILS Requested funds will be used to develop/support:   GC/CM support to prepare design and construction documents from 30% to issue for construction Pre-construction work packages This commission action will provide for GC/CM contract execution and pre-construction support services through the duration of the design. Scope of Work Concourse HVAC Infrastructure Renewal Replacement Program will focus on HVAC replacement, ceiling and lighting replacement, ceiling mounted fixtures replacement and Fire code (smoke control exhaust and sprinklers). The scope of work will include: Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA - Action Item No. 10a Meeting Date: July 8, 2025 Page 3 of 6 (1) (2) (3) (4) Replacement of existing air handlers on concourse B, C and D. Addition of supplemental air handlers during change outs. Sizing adjustment of select terminal units for air distribution. Upsizing chilled water and hydronic heating water distribution. Heat trace on chilled water line on the roof. (5) Emergency power system upgrades (panels, distribution gear, and step-down transformers. At a minimum, two separate power sources.) (6) Addition of active smoke control and/or smoke management systems. (7) Distribution ducting upsizing as required, including ceiling diffusers. (8) Ceiling replacement within the concourses (not including hold rooms). (9) Structural upgrade to support new Penthouses, plus seismic upgrades required by the latest building code. (10) Fire sprinklers and fire riser upgrades. (11) Refreshed exit signage. (12) Column cover replacements as needed. (13) Upgraded lighting to LED & new lighting control systems. (14) Waste and ventilation pipe replacement where impacted. (15) Security camera updates. (16) Demolition of abandoned conduit & utilities. (17) Compliance with upcoming State of Washington Clean Buildings Performance Standard will identify energy efficiency measures that may need to be added to CHIRRP's scope for implementation. Schedule The current project schedule shows an in-use date Q3 2034. The dates shown below are based on conservative assumptions in procurement, permitting, and construction. Options to further compress the schedule will be evaluated during the planning phase. Activity Construction starts In-use date 2029 Quarter 1 2034 Quarter 3 Cost Breakdown This Request Total Project Design Construction Total $11,000,000 0 $11,000,000 TBD in 30% Design TBD in 30% Design $255M-$450M Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA - Action Item No. 10a Meeting Date: July 8, 2025 Page 4 of 6 ALTERNATIVES AND IMPLICATIONS CONSIDERED Alternative 1 - Status Quo, Do not proceed with this project. Cost Implications: Approximately $2,108,028 would need to be expensed. Pros: (1) Cons: (1) (2) (3) (4) (5) No further capital investment required at this time. Passenger comfort would continue to worsen. AHU(s) failures will lead to extended outages (months). High risk shutdown of concourse/s due to poor air quality. High risk of emergency repairs required to maintain airport operations. No Smoke Control on Concourses may result in complete evacuation in the event of minor fires. This is not the recommended alternative. Alternative 2 - Full Design - Complete concourse B, C and D. Pros: (1) (2) (3) (4) (5) (6) (7) Improved passenger comfort. All concourses, smoke control exhaust and sprinklers included. All concourses, spare capacity to add additional kitchen exhaust, bathroom exhaust, etc. Allows for the Central Plant decarbonization effort - reduces SEA carbon footprint. Qualify for rebates for the updated AHUs and new lighting. New lighting provides improved illumination in dark areas on the concourses. Most structural columns will be updated with seismic. Cons: (1) (2) (3) Large capital investment. Construction expected to take 3 years. Extensive coordination required during construction. This is the recommended alternative. Alternative 3 - Build to Budget - cut/defer scope with temporary measures proposed to phase or delay capital spending. Pros: (1) (2) Better passenger comfort in the areas updated. Fire protection, sprinklers, and smoke control would exist in those areas like Concourse A. Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA - Action Item No. 10a Meeting Date: July 8, 2025 Cons: (1) (2) (3) (4) (5) (6) Page 5 of 6 Risk shutdown of concourse due to poor air quality. Large Capital investment is required. Some essential scope may need to be eliminated. This may result in equipment failures and emergency repairs leading to extended outages. Project execution would need to be highly coordinated between airlines and operations. Requires future project to complete full scope. Highest Life Cycle Cost. This is not the recommended alternative. FINANCIAL IMPLICATIONS Following a third-party cost estimate, as part of the 30% Design, the project will update the revised estimate for total project cost. Cost Estimate/Authorization Summary COST ESTIMATE Original estimate Current Budget Estimate Revised estimate Capital Expense Total $255,000,000 TBD TBD $0 $0 $0 $255,000,000 $0 $255,000,000 $450,000,000 $7,250,000 $11,000,000 $18,250,000 TBD $0 $0 $0 $0 $7,250,000 $11,000,000 $18,250,000 TBD AUTHORIZATION Previous authorizations Current request for authorization Total authorizations, including this request Remaining amount to be authorized Annual Budget Status and Source of Funds This project #C801265 was included in the 2025-2029 capital budget and plan of finance with budget of $255,000,000. This project will be funded by the Airport Development Fund (ADF) and revenue bonds. Financial Analysis and Summary Project cost for analysis Business Unit (BU) $255,000,000 - $450,000,000 Terminal Building Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA - Action Item No. 10a Meeting Date: July 8, 2025 Effect on business performance (NOI after depreciation) IRR/NPV (if relevant) CPE Impact Page 6 of 6 NOI after depreciation will increase due to inclusion of capital (and operating) costs in airline rate base. N/A $0.63 to $1.08 in 2032 Future Revenues and Expenses (Total cost of ownership) Aviation Operations and Maintenance have reviewed the preliminary design of the system, and meetings have been held with leadership from each group to discuss expected additional costs of ownership. A full evaluation of the future expenses will be provided with the completed Project Notebook. ATTACHMENTS TO THIS REQUEST (1) Presentation PREVIOUS COMMISSION ACTIONS OR BRIEFINGS March 14, 2023 (item 8k) - The Commission authorized the Executive Director to (1) advertise and execute a project specific contract for Architecture and Engineering (A&E) services, (2) develop a Project Definition Document and progress the overall design to 30%, (3) utilize port crews for enabling work related to the Concourse HVAC Infrastructure Renew/Replace (CHIRRP) project at Seattle-Tacoma International Airport. The amount being requested under this authorization was $7,250,000. Template revised June 27, 2019 (Diversity in Contracting).