
COMMISSION AGENDA – Action Item No. 8d Page 4 of 5
Meeting Date: June 24, 2025
Template revised June 27, 2019 (Diversity in Contracting).
Cons:
(1) The most expensive option.
This is not the recommended alternative.
Alternative 3 – Refurbish approximately the first 6 units and fully replace the remaining 10 units
at all gates.
Cost Implications: This would be less costly than the second alternative of full replacement but
more expensive than the first alternative of full refurbishment.
Pros:
(1) Fastest completion date of any alternative.
(2) Cheaper than the full replacement alternative.
Cons:
(1) Refurbished units will have a lower lifecycle of the asset than a fully replaced unit,
potentially resulting in failing units again.
(2) Refurbished units have unknown risks to functionality.
(3) Refurbished units will have longer gate downtime than replacement of units, and
therefore slightly increased operational impacts.
This is the recommended alternative.
/Authorization Summary Capital
Expense
Total
COST ESTIMATE
Original estimate $4,065,387
$0
$4,065,387
AUTHORIZATION
Previous authorizations $0
$0
$0
Current request for authorization $4,065,387
0
$4,065,387
Total authorizations, including this request $4,065,387
0
$4,065,387
Remaining amount to be authorized $0
$0
$0
Annual Budget Status and Source of Funds
This project #C802126 was not included in the 2025-2029 capital budget and plan of finance. A
budget of $4,065,387 was transferred from the Aeronautical Allowance
1
CIP C800753 resulting
in zero net change to the Aviation capital budget. This project will be funded by the Airport
Development Fund (ADF).
Financial Analysis and Summary
1
The Aeronautical Allowance is included in the Capital Improvement Plan to ensure funding capacity for
unspecified projects, cost increases for existing projects, new initiatives, and unforeseen needs. This ensures funding
capacity for unanticipated spending within the dollar amount of the Allowance CIP.