Item No. Date of Meeting SCE Final Design Funding Request Authorization 8f_supp May 27, 2025 Commission Request • Request Commission authorization for the Executive Director to (1) increase funding to complete S Concourse Evolution base building design, (2) execute a professional services contract for design services and construction bid packages for the A6 Widebody Remediation, (3) advertise and execute construction contracts for Cargo 3, Cargo 6, and gate D6, (4) advertise and execute a program specific contract for special testing and inspection, (5) modify the existing United Airlines lease for the cargo 3 maintenance facility, (6) transfer scope and budget of $25M from CIP C801375 to CIP C801203 for gate A6 Widebody Remediation. The total amount of this request is $125,000,000. 2 Facilitating Projects Addressing Construction Impacts • Improve existing Cargo 7 and provide Short-Term Holdroom (A Annex) serving 4 aircraft positions • Improve existing Cargo 6 location to allow for Passenger Operations • Convert existing Gate D6 from a bussing gate back to a Passenger Loading Bridge • Convert existing parking area at Cargo 3 for GSE Storage Cargo 7 & Short-Term Holdroom Cargo 6 Cargo 3 GSE Parking Gate D6 Conversion 3 Gate A6 Modifications • Scope will be added to the SCE Program to support larger (widebody) types of international aircraft. • Project will remove part of Gate pod A to increase the nose-to-building clearance to ~28 feet. 4 SCE Funding Allocation - 125M Request Project Completion of Base Building and A6 Design Construction at Cargo 3, Cargo 6, and Gate D6 Construction Management Support and Service Directive (Jacobs) Budget $75,000,000 $30,000,000 $20,000,000 5 Thank you! 6