Parking Garage Rehabilitation (#C801307)
Design Authorization
8d_supp
Item No.
May 27, 2025Date of Meeting
Parking Garage Rehabilitation
Request Commission Authorization for Executive Director to
complete the design for the Parking Garage Rehabilitation
project at Seattle-Tacoma International Airport for a total
authorization of $8,885,000.
2
Project Location
3
Structure
Existing Conditions
Fire Suppression Ventilation
4
Lift Station
Existing Conditions (Continued)
Expansion Joints Plumbing
5
Project Budget and Schedule
6
Project Budget : $55,709,000
Previous Request: $ 2,100,000
This Request: $ 6,785,000
Total Authorized: $ 8,885,000
Project is on budget
Preliminary Project Schedule:
• Design Complete Q4 2026
• Construction Auth. Q4 2026
• Begin Construction Q1 2027
• Complete Construction Q1 2030
Cone of Certainty
7
We are here