COMMISSION
AGENDA MEMORANDUM
Item No. 8d
ACTION ITEM Date of Meeting May 13,2025
DATE: April 23, 2025
TO: Stephen P. Metruck, Executive Director
FROM: Jennifer Maietta, Director, Real Estate Asset Management
Jessica Carlson, Sr. Real Estate Manager
Terrence Moody, Capital Project Manager
SUBJECT: Fishermen’s Terminal ADA Compliance Phase 2 Additional Funding Request
(CIP# C801198) (Short Form)
Amount of this request: $350,000
Total ADA Phase 2 estimated project cost:
Total ADA Phase 1 project cost: $1,594,101
$1,605,899
Total estimated project cost (Phase 1 & 2): $3,200,000
ACTION REQUESTED
Request Commission authorization for the Executive Director to authorize additional funding in
the amount of $350,000 to complete additional scope of work for the construction of the entry
area to the former Highliner at the C-15 Building at Fishermen’s Terminal (FT) as part of the Phase
2 FT ADA Compliance Project (C801198).
The amount of this request is $350,000 for a Phase 2 total project authorization of $1,605,899.
The Phase 1 project costs were $1,594,101 for a combined project total of $3,200,000.
SUMMARY
Additional funding is required to complete the necessary ADA compliance construction at the
former Highliner (C-15) entryway to ensure safe and equitable access for FT employees, tenants,
and visitors. Post Phase 1 construction there were numerous deficiencies found as part of the
University of Washington Accessible Design and Innovative Inclusion (UW-ADII) post-
construction inspections. Therefore, Phase 2 was required to correct the noted deficiencies.
During Phase 2, the sidewalk area near the Highliner was not identified as a deficient area and
therefore was not included in the Phase 2 design. This area, however, was included in the litigant
COMMISSION AGENDA – Action Item No. 8d Page 2 of 2
Meeting Date: May 13, 2025
Template revised September 22, 2016; format updates October 19, 2016.
scope but not completed during Phase 1. Thus, this additional scope is required to ensure
compliance with all identified non-compliant ADA areas. During Phase 2 construction this area
was surveyed and confirmed by the contractor to be non-ADA compliant. The Port construction
management team has confirmed these findings based on its own recent site survey and agrees
with the contractor’s assessment. As a result, this small section of sidewalk is now being added
as an additional scope of work to maximize efficiencies with the onsite Phase 2 construction. The
additional funding will allow the project to be completed by June 30, 2025.
There are no attachments to this memo.
PREVIOUS FUNDING ACTIONS OR BRIEFINGS
September 22, 2020 – Commission: Settlement Agreement ($1,530,000)
October 16, 2020 – Project Seed Funding ($85,000)
April 13, 2021 – Commission: Design Funding ($215,000)
March 22, 2022 – Commission: Construction Funding ($850,000)
November 29, 2022 – Commission: Additional Construction Funding ($600,000)
April 16, 2024 – Commission: Phase 2 Funding ($1,100,000)