Template revised April 12, 2018.
COMMISSION
AGENDA MEMORANDUM
Item No. 8d
ACTION ITEM Date of Meeting May 13,2025
DATE: April 23, 2025
TO: Stephen P. Metruck, Executive Director
FROM: Jennifer Maietta, Director, Real Estate Asset Management
Jessica Carlson, Sr. Real Estate Manager
Terrence Moody, Capital Project Manager
SUBJECT: Fishermen’s Terminal ADA Compliance Phase 2 Additional Funding Request
(CIP# C801198) (Short Form)
Amount of this request: $350,000
Total ADA Phase 2 estimated project cost:
Total ADA Phase 1 project cost: $1,594,101
Total estimated project cost (Phase 1 & 2): $3,200,000
ACTION REQUESTED
Request Commission authorization for the Executive Director to authorize additional funding in
the amount of $350,000 to complete additional scope of work for the construction of the entry
area to the former Highliner at the C-15 Building at Fishermen’s Terminal (FT) as part of the Phase
2 FT ADA Compliance Project (C801198).
The amount of this request is $350,000 for a Phase 2 total project authorization of $1,605,899.
The Phase 1 project costs were $1,594,101 for a combined project total of $3,200,000.
SUMMARY
Additional funding is required to complete the necessary ADA compliance construction at the
former Highliner (C-15) entryway to ensure safe and equitable access for FT employees, tenants,
and visitors. Post Phase 1 construction there were numerous deficiencies found as part of the
University of Washington Accessible Design and Innovative Inclusion (UW-ADII) post-
construction inspections. Therefore, Phase 2 was required to correct the noted deficiencies.
During Phase 2, the sidewalk area near the Highliner was not identified as a deficient area and
therefore was not included in the Phase 2 design. This area, however, was included in the litigant