COMMISSION AGENDA MEMORANDUM Item No. ACTION ITEM Date of Meeting DATE: April 11, 2025 TO: Stephen P. Metruck, Executive Director FROM: Eileen Francisco, Director, Aviation Project Management Keri Stephens, Director, Aviation Facilities and Capital Programs 8e April 22, 2025 SUBJECT: Water Reservoir Rehabilitation CIP #C801172 Additional Authorization Request Amount of this request: Total estimated project cost: $1,600,000 $5,169,000 ACTION REQUESTED Request Commission authorization for the Executive Director to increase the Capital Improvement project authorization for the Water Reservoir Rehabilitation project by $1,600,000. The amount of this request is for $1,600,000 for a revised total estimated project cost not to exceed $5,169,000. SUMMARY The 2-million-gallon water reservoir at Seattle-Tacoma International Airport is an above ground steel tank that provides water storage for domestic use and fire suppression to the entire airport. This project will rehabilitate the structure to extend its useful life. The scope of this project was based off a September 2021 inspection report which indicated that severe corrosion has appeared in many areas on the reservoir and, if not addressed, could result in deformation of the structure. The presence of rust also puts the water quality into jeopardy. Roof repairs in addition to the coating replacement were not included in the report but became apparent once the contractor entered the tank and evaluated the current tank conditions. The project was advertised for bids on July 9th, 2024, and was awarded to T-Bailey on August 29, 2024. The contractor mobilized and entered the tank to examine existing conditions on January 21, 2025, when they observed severe corrosion of the roof. A full roof replacement was recommended since it would be significantly more costly to repair the existing roof structure. On January 28th, 2025, the project structural engineer arrived on site to visually inspect the roof and concurred that, due to the amount of corrosion, the roof requires replacement. A change order will be developed to execute this work. There are no attachments to this memo. Template revised April 12, 2018.