COMMISSION
AGENDA MEMORANDUM Item No. 8b.3
ACTION ITEM Date of Meeting April 22, 2025
DATE: April 15, 2025
TO: Steve Metruck, Executive Director
FROM: Eloise Olivar, AFR Assistant Director Disbursements
SUBJECT: Claims and Obligations – November 2024
ACTION REQUESTED
Request Port Commission approval of the Port Auditor’s payment of the salaries and claims of the Port
pursuant to RCW 42.24.180 for payments issued during the period November 01 through 30, 2024 as
follows:
Payment Type Payment Reference
Start Number
Payment
Reference End
Number
Amount
Accounts Payable Checks 955311 955645 $11,575,279.52
Accounts Payable Manual Checks
102180 102221 $623,712.88
Accounts Payable ACH 069210 069870 $67,724,687.92
**Accounts Payable Electronic
069374 SXL383-410 $35,153,863.39
226615 227140 $324,543.57
1216143 1222704 $17,586,776.48
Total Payments
$132,988,863.76
**This line item includes four wire transfer totaling $6,068,870.00. Due to recovery from system outage, new series of payment reference numbers
were generated.
Pursuant to RCW 42.24.180, “the Port’s legislative body” (the Commission) is required to approve in a public
meeting all payments of claims within one month of issuance.
OVERSIGHT
All these payments have been previously authorized either through direct Commission action or delegation
of authority to the Executive Director and through his or her staff. Detailed information on Port expenditures
is provided to the Commission through comprehensive budget presentations as well as the publicly released
Budget Document, which provides an even greater level of detail. The Port’s operating and capital budget is
approved by resolution in December for the coming fiscal year, and the Commission also approves the Salary
and Benefit Resolution around the same time to authorize pay and benefit programs. Notwithstanding the
Port’s budget approval, individual capital projects and contracts exceeding certain dollar thresholds are also
subsequently brought before the Commission for specific authorization prior to commencement of the
project or contract—if they are below the thresholds the Executive Director is delegated authority to approve
them. Expenditures are monitored against budgets monthly by management and reported comprehensively
to the Commission quarterly.