Item No. 10d_supp Date of Meeting April 22, 2025 Baggage Optimization Program Phase 3 April 22, 2025 Baggage Optimization Purpose and Scope • Purpose: • Airport wide public safety and security program that improves customer service for both airlines and passengers by providing flexibility, reliability, and efficiency. • Scope: • The Baggage Optimization project replaces six individual baggage screening systems with a centralized system that optimizes the operation and functionality of the checked baggage system. 2 Phase 1 • • • • • • • Contract Method: Design/Bid/Build Construction completed 2020 Installed 8 new baggage screening machines Constructed new building extension to Central Terminal Constructed new Checked Baggage Resolution Area for TSA Constructed new Maintenance breakrooms & locker rooms Constructed new TSA breakrooms Phase 2 • • • • • • Contract Method: Design/Bid/Build Construction Completed in 2024 Installed 4 baggage screening machines Constructed new tenant storage & maintenance shop Baggage handling system sortation matrix was constructed Added additional baggage capacity to South Satellite 3 Phase 3 • • • • • Contract Method: General Contractor/Construction Manager (GC/CM) Demolish and connect the two final baggage systems, C60 and C61 Modify the International Arrivals Facility (IAF) Baggage Handling System to facilitate both IAF and final sortation destination makeup devices Update upper-level controls for entire system Make all ticket counter and sortation final connections for a fully optimized system 4 Phase 3 Schedule Commission Current Schedule GC/CM Pre-Construction Contract Execution Q3 2023 Q3 2023 Design Finish Q4 2024 Q1 2025 Permit has not been issued MACC Negotiation Complete Q4 2024 Q1 2025 Extended negotiations to reduce estimate by $97M GC/CM Contract Execution Q4 2024 Q2 2025 GC/CM NTP Q4 2024 Q3 2025 Substantial Completion Q2 2027 Q4 2029 Milestone (March 2024) Notes Contractor increased Construction duration 5 Program Budget Project Name Budget Current Estimate Over/Under Budget Baggage Optimization Phase 1 $101,375,000 $97,638,982 $(3,736,018) Baggage Optimization Phase 2 $395,675,000 $376,000,000 $(19,675,000) Baggage Optimization Phase 3 $432,450,000 $585,500,000 $153,050,000 CCE Transfer Line $15,500,000 $15,500,000 $0 Baggage Optimization Executive Management Reserve $10,000,000 $0 $(10,000,000) $955,000,000 $1,074,638,982 $119,638,982 (13%) Total 6 Request • Request Commission authorization for the Executive Director to take all steps necessary, including the execution of all contracts, including Public Works, Alternative Public Work procedures in accordance with RCW 29.10, Goods and Services Personal Services, Professional Services, other consulting services, and any other types of contracts or agreements to complete the Baggage Optimization Program Phase 3 for a total Program budget of $1,074,638,982. 7