COMMISSION AGENDA – Action Item No. 10d Page 6 of 7
Meeting Date: April 22, 2025
Template revised June 27, 2019 (Diversity in Contracting).
July 26, 2022 – Request Commission authorization for the Executive Director to: (1)
execute an agreement with the Transportation Security Administrative (TSA) to provide
clear access to screening equipment for Phase 2, (2) authorize $34,215,000 for Phase 3
to complete pre-construction services, (3) utilize, advertise, and execute a General
Contractor/Construction Manager (GC/CM) for Phase 3, (4) advertise and execute a
project specific Construction Management (CM) and Airline Technical Representative
(ATR) contract for Phase 3, (5) amend Service Agreement (SA) P-00317641 to add
$18,340,000 for a total contract value of $49,500,000 to complete design services and
provide construction support for Phase 3, and (6) utilize Port crews for Phase 3
activities, for Baggage Optimization Project at Seattle-Tacoma International Airport. The
total amount of this request is $34,215,000.
April 19, 2022 – Baggage Optimization Program Update – Quarter 2, 2022.
January 28, 2020 – Commission Authorization to: (1) execute a construction contract
with the low responsive and responsible bidder for the Baggage Optimization Phase 2
Project at Seattle-Tacoma International Airport, notwithstanding the low bid
exceeding the estimate at time of bid by more than 10 percent, and (2) authorize an
additional $190,737,800 for Phase 2 construction and Phase 3 design for a total
program authorization of $540,050,000.
April 23, 2019 – Commission Authorization to: (1) advertise, award, and execute a
construction contract for the Baggage Optimization Phase 2 project at Seattle-Tacoma
International Airport; (2) employ a project labor agreement (PLA); and (3) utilize Port
crews and small works contracts to perform construction work.
February 26, 2019 – Baggage Optimization Quarter 4 Project Briefing.
October 23, 2018 – Baggage Optimization Quarter 3 Project Briefing.
June 12, 2018 – Baggage Optimization Quarter 2 Project Briefing.
January 9, 2018 – Baggage Optimization Quarter 4 Project Briefing.
September 26, 2017 – Baggage Optimization Quarter 3 Project Briefing.
June 27, 2017 – Commission authorization to (1) authorize additional design and project
management funds to expand the capacity to 60 million annual passengers (MAP); (2)
use Port crews and small works contracts to perform additional construction work; and
(3) amend Service Agreement P-00317641 to add $10,160,000.
October 25, 2016 – Baggage Optimization Quarter 4 Project Briefing.
July 12, 2016 – Commission authorization to advertise and execute a contract for
Construction Phase 1.
June 28, 2016– Baggage Program Briefing.
May 17, 2016 – Checked Baggage Optimization Project Briefing.
March 8, 2016 – Commission authorization for the Chief Executive Officer to amend the
Baggage Optimization Design Services contract.
June 23, 2015 – Checked Baggage Optimization Project Briefing.
September 10, 2013 – The Commission authorized the execution of an
Other Transaction Agreement (OTA) with TSA for reimbursable costs for design and
construction, to authorize $15 million to continue from 30% to 100% design and execute
a consultant service agreement for program management support services.