STS – Dry Fire Suppression System Upgrades
C801429
Regulatory Funding Request
8d_supp
Item No.
April 8, 2025Date of Meeting
Project Purpose and Scope
Purpose:
To bring the STS dry fire standpipe systems up to operational pressure standards per NFPA
25 code in all three STS train tunnels; South, North, and Shuttle.
Project Scope:
2
• Inspect pipe and fittings for excessive corrosion
and pinholes
• Replace any identified deficiencies including:
– existing couplings
– hose valves
– check valves
Project Location
Satellite Transit System (STS)
• South Loop
• North Loop
• Shuttle
3
24
th
Ave S
N
Project Budget
4
Previous Executive Authorized Budget $1,971,000
Current Request for Authorization $2,029,000
Total Project Cost $4,000,000
Project Schedule
5
Cost Certainty
6
NEPL Phase 3
Questions?
7