Item No. 8g_supp Meeting Date: March 11, 2025 Generator Controls Upgrade (C801316 | N03387) Project Authorization Hien Mac AV F&I - Electrical Manager Matthew Piccolo AV PMG Capital Project Manager Project Background • The Concourse A and Combined Communications and Control Center (C4) generator control systems are nearly 20 years old and are still operated by the original programable logic controllers (PLC). These PLCs are at end of life and no longer available. o • The Airport moved to a new standard controls for generators in 2018 (Allen Bradley). • These generators provides back-up power to life safety items such as egress lighting, fire alarms, radio systems, evacuation elevators, exit doors, fire pumps, and the ACC, ECC, and 911 dispatch in the C4. 2 Project Justification, Purpose, and Scope Justification: The project is a regulatory requirement. Emergency power generation is required by the National Electrical Code (NEC) and the National Fire Protection Association (NFPA) for all life-safety systems. Purpose: This project will replace the existing obsolete controls with new standardized hardware and rectify non-compliant portions of the system. Scope: • Replace end of life PLCs • Integrate generator operation status and support systems into the Direct Digital Control (DDC) system for remote monitoring during disruptions • Correct NFPA non-compliant issues in the generator rooms 3 Project Location Continued 4 Project Location 1 2 1 2 5 Schedule Overview Delivery Method: Building Engineered Systems (BES) Requested Authorization Authorization Project Phase Capital Expense Total Previous Authorizations Notebook + Basis of Design $950,000 $0 $950,000 Current request for Authorization Advertise BES Contract, Final Design, Construction, & Closeout $8,325,000 $125,000 $8,450,000 Total authorizations, including this request Notebook + Design + Construction + Closeout $9,275,000 $125,000 $9,400,000 Remaining amount to be authorized N/A $0 $0 $0 7 Cone of Certainty We are here 8 Action Requested • Prepare, Advertise, and Execute a Public Works Building Engineering Systems Contract • Execute related project change orders, amendments, work authorizations, purchases, contracts, and take other actions necessary to support and deliver the generator controls project within the approved budget • Utilize Port of Seattle crews, and small and major works on-call contracts, to support design and construction activities. • Requesting authorization of $8,450,000 for a total project authorization not to exceed $9,400,000. 9 QUESTIONS? 10