COMMISSION AGENDA MEMORANDUM Item No. ACTION ITEM Date of Meeting DATE: February 27, 2025 TO: Stephen P. Metruck, Executive Director FROM: Keri Stephens, Director Aviation Facilities and Capital Programs Eileen Francisco, Director Aviation Project Management 8c March 11, 2025 SUBJECT: Bldg. 161G AV Facility Upgrade (CIP#C800924) - Construction Claim (Short Form) Amount of this request: Total estimated project cost: $250,000 $4,022,000 ACTION REQUESTED Request Commission authorization for the Executive Director to increase the Capital Improvements project budget for the Building 161G AV Facility Upgrade project by $250,000 for a revised total budget of $4,022,000. SUMMARY The Bldg. 161G Aviation Maintenance Facility Upgrade project has completed physical construction and is in the process of closeout. This project installed new heating, ventilation, and air conditioning (HVAC) systems to service the breakrooms and office spaces and upgraded the wireless communication infrastructure. This request for additional funds is for a late-term claim that was submitted by the contractor. The claim is for unforeseen conditions including temporary trailer placement and abatement work that was required to complete the upgrades. The additional funds will be applied to final negotiated amount of claim and Port overhead. This project is seeking additional funds to cover and settle claim and completely close-out the project, no additional work is associated with this request. There are no attachments to this memo. Template revised April 12, 2018.